Detailed design and survey - Remedial stormwater drainage in Odessa West neighbourhood
Federal contribution
$30,000
Federal share50%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Loyalist
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Jul 26, 2019(actual)
Against the original forecast
- Construction start10 months lateforecast Feb 1, 2017
- Construction end5 months earlyforecast Dec 13, 2019
Also in Loyalist
- Construction of a Sustainable Community Hub in Loyalist Township - Retrofit$16.6M
- Hyland and Briscoe Rehabilitation$913.8K
- Detailed design and construction - Water main relining on Cambridge Crescent$302.1K
- Installation of stormwater infrastructure on Davy Street$255.7K
- Installation of stormwater infrastructure and water and sewer main replacement on Frink Avenue$175.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49138 in the federal list. How to read these figures.