Clarifier Design & Environmental Assessment - Wastewater Plant Improvements

West Perth, Ontario

completeWastewaterCWWF
Federal contribution
$198,854
Federal share50%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of West Perth
Construction start
Jun 5, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start9 months lateforecast Sep 1, 2016