Back to projects

The Simcoe Road Stormwater Management Facility Remediation and Restoration

Bradford West Gwillimbury, Ontario

completeWastewaterCWWF
Federal contribution
$89,215
Federal share24%

of $373.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 6, 2017(actual)
Construction end
Oct 15, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2017
  • Construction end9 months lateforecast Dec 31, 2017

Also in Bradford West Gwillimbury