Frances St Watermain Replacement

West Perth, Ontario

completeDrinking WaterCWWF
Federal contribution
$180,746
Federal share50%

of $361.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2017
ApprovedMar 27, 2018
20172018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of West Perth
Construction start
Jan 2, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Dec 1, 2016
  • Construction end9 months earlyforecast Sep 30, 2018