Back to projects

Replacement of existing Marine Drive Bridge over Mosquito Creek

North Vancouver, British Columbia

completeHighways and RoadsSCF
Federal contribution
$1.9M
$1,933,333
Federal share33%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
2018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of North Vancouver
Construction start
Sep 3, 2019(actual)
Construction end
Mar 31, 2021(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 15, 2019
  • Construction end3 weeks lateforecast Mar 12, 2021

Also in North Vancouver