Pinecrest Estates Wastewater Treatment Plant (Sewer) Replacement

Whistler, British Columbia

completeWastewaterCWWF
Federal contribution
$998,205
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jan 3, 2018(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 30, 2017

Also in Whistler