Stormwater Management Phase 4
Williams Lake, British Columbia
Federal contribution
$269,515
Federal share50%
of $539.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Williams Lake
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Feb 7, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 14, 2017
- Construction end7 weeks lateforecast Dec 19, 2018
Also in Williams Lake