Water Management Strategy
Williams Lake, British Columbia
Federal contribution
$81,099
Federal share48%
of $167.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Williams Lake
- Construction start
- Aug 8, 2017(actual)
- Construction end
- Jul 30, 2019(actual)
Against the original forecast
- Construction start6 months earlyforecast Feb 1, 2018
- Construction end8 months earlyforecast Mar 31, 2020
Also in Williams Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49852 in the federal list. How to read these figures.