Design for a new water treatment plant to replace existing aging plant
Federal contribution
$11,194
Federal share50%
of $22.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Val Rita-Harty
- Construction start
- Dec 15, 2017(actual)
- Construction end
- Dec 15, 2019(actual)
Against the original forecast
- Construction start10 months lateforecast Feb 15, 2017
- Construction end2 months lateforecast Sep 30, 2019
Also in Val Rita-Harty
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51200 in the federal list. How to read these figures.