Back to projects

Glacier 1 (Elevator and HVAC Upgrades)

Mount Pearl, Newfoundland and Labrador

completeRecreationSCF
Federal contribution
$128,088
Federal share26%

of $498.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018201920202021
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Mount Pearl
Construction start
Jun 1, 2019(actual)
Construction end
Feb 10, 2021(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2019
  • Construction end22 months earlyforecast Nov 30, 2022

Also in Mount Pearl

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51580 in the federal list. How to read these figures.