2017 - 2020 Street Upgrading (Second Street between St. Andrews and Sunrise)

Mount Pearl, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$143,764
Federal share22%

of $639.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Mount Pearl
Construction start
Oct 30, 2018(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 30, 2018
  • Construction end7 weeks lateforecast Aug 15, 2020

Also in Mount Pearl

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51584 in the federal list. How to read these figures.