Water Drainage - Old Hospital Site

Fogo Island, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$38,119
Federal share33%

of $114.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Fogo Island
Construction start
Oct 1, 2018(actual)
Construction end
Nov 18, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Aug 15, 2018
  • Construction end3 weeks lateforecast Oct 31, 2018