Iceberg Arena Upgrades

Fogo Island, Newfoundland and Labrador

completeRecreationSCF
Federal contribution
$57,026
Federal share30%

of $190.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Fogo Island
Construction start
Sep 1, 2018(actual)
Construction end
Feb 8, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 30, 2018
  • Construction end11 months earlyforecast Dec 30, 2019

Also in Fogo Island

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51658 in the federal list. How to read these figures.