Back to projects

Dumaresque Street, Murray Avenue, and Bridge Street - Water and Sewer Replacement

Bathurst, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$165,000
Federal share50%

of $330.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2018
2018
Built

Approved 10 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Bathurst
Construction start
Aug 1, 2017(actual)
Construction end
Oct 27, 2017(actual)

Also in Bathurst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51851 in the federal list. How to read these figures.