Back to projects

Reconstruction of Nelson Street from Mosher Avenue to 90m West

Fort Frances, Ontario

completeWastewaterCWWF
Federal contribution
$148,424
Federal share21%

of $723.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
2018
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Fort Frances
Construction start
May 15, 2017(actual)
Construction end
Nov 29, 2018(actual)

Against the original forecast

  • Construction end5 months lateforecast Jun 30, 2018

Also in Fort Frances

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52130 in the federal list. How to read these figures.