Telly Roads Aquaduct in Rivière-à-la-Truite Regional Municipality of Tracadie
Tracadie-Sheila, New Brunswick
Federal contribution
$25,185
Federal share50%
of $50.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 5, 2019
20192020
Built
Approved 17 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Grand Tracadie-Sheila
- Construction start
- Apr 15, 2019(actual)
- Construction end
- Dec 23, 2019(actual)
Against the original forecast
- Construction end8 weeks lateforecast Oct 31, 2019