Potable Drinking Water Unit Fogo Island
Fogo Island, Newfoundland and Labrador
Federal contribution
$27,261
Federal share40%
of $68.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Apr 1, 2021(actual)
- Construction end
- May 7, 2021(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2021
- Construction end5 months earlyforecast Sep 30, 2021