New Smart Accessible Playground Installation
Mount Pearl, Newfoundland and Labrador
Federal contribution
$151,169
Federal share33%
of $453.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Mount Pearl
- Construction start
- Oct 8, 2021(actual)
- Construction end
- Sep 23, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 14, 2021
- Construction end2 months lateforecast Jul 22, 2022
Also in Mount Pearl
- Arena and Pool$4.0M
- Commonwealth Avenue Infrastructure Improvements$2.7M
- Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement Farrell Drive (from Holden Street to Evans Place)$2.5M
- Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement Spruce, Birch, Roosevelt Avenues; and Carroll Drive; and Watermain Lining Billard Avenue$2.4M
- Street Improvements$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53878 in the federal list. How to read these figures.