Metro Vancouver Regional District - Grouse Mountain Regional Park - Trail and Amenity Improvements

North Vancouver, British Columbia

completeActive TransportationCCRIS
Federal contribution
$1.4M
$1,390,750
Federal share40%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022202320242025
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Metro Vancouver
Construction start
Apr 27, 2020(actual)
Construction end
Dec 20, 2024(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast May 15, 2020
  • Construction end3 months earlyforecast Mar 31, 2025