Conventional Vehicle Replacement - 2021
Federal contribution
$3.2M
$3,159,408
Federal share40%
of $7.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2020
20212022202320242025
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Oakville
- Construction start
- Jan 7, 2021(actual)
- Construction end
- Jan 27, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Oct 20, 2020
- Construction end4 months lateforecast Sep 30, 2024
Also in Oakville