Conventional Vehicle Expansion
Federal contribution
$3.0M
$2,996,000
Federal share40%
of $7.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2020
202120222023202420252026
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Oakville
- Construction start
- Sep 30, 2021(actual)
- Construction end
- Dec 31, 2025(forecast)
Also in Oakville