Facility & Onboard WiFi with Automated Video Conversion of Display Wall to LED
Federal contribution
$350,953
Federal share40%
of $877.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2020
20212022
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Oakville
- Construction start
- Aug 27, 2021(actual)
- Construction end
- Nov 24, 2022(actual)
Against the original forecast
- Construction start13 months lateforecast Jul 22, 2020
- Construction end2 months earlyforecast Jan 31, 2023