Thompson Okanagan Indigenous Cultural Centre - Phase 1

Kelowna, British Columbia

completeGreen EnergyGIS
Federal contribution
$91,891
Federal share40%

of $229.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 8, 2021
20212022
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 30, 2021(actual)
Construction end
Jul 30, 2022(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Mar 15, 2021
  • Construction end4 weeks lateforecast Jul 1, 2022