Facility Fixture conversion and HVAC Upgrades
Federal contribution
$1.1M
$1,139,925
Federal share80%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Oakville
- Construction start
- Sep 28, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Also in Oakville