Dykeland Lodge - Facility Upgrade - Phase 2

Windsor, Nova Scotia

completeHealthcare InfrastructureCVRIS
Federal contribution
$8,618
Federal share80%

of $10.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Dykeland Lodge
Construction start
Oct 1, 2021(actual)
Construction end
Oct 8, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2021
  • Construction end3 months earlyforecast Dec 30, 2021

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60545 in the federal list. How to read these figures.