District of North Vancouver - Livable Deep Cove Covid Resilience

North Vancouver, British Columbia

completeActive TransportationCVRIS
Federal contribution
$2.7M
$2,655,480
Federal share80%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 11, 2021
20222023
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
District of North Vancouver
Construction start
Feb 13, 2023(actual)
Construction end
Oct 11, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jan 11, 2023
  • Construction end3 months earlyforecast Dec 31, 2023

Also in North Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60553 in the federal list. How to read these figures.