Kelowna - Rutland to Okanagan Rail Trail Shared Pathway
Federal contribution
$2.0M
$1,950,514
Federal share80%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Kelowna
- Construction start
- Jun 6, 2022(actual)
- Construction end
- Dec 1, 2022(actual)
Against the original forecast
- Construction end11 months earlyforecast Oct 31, 2023
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60554 in the federal list. How to read these figures.