Kelowna RapidBus Shelters
Federal contribution
$98,676
Federal share40%
of $246.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2021
2022
Built
Approved 3 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Feb 23, 2022(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 15, 2021
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60988 in the federal list. How to read these figures.