Trails and Active Transportation Plan for Trent Hills, Ontario
Federal contribution
$33,000
Federal share83%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of Trent Hills
- Construction start
- Aug 22, 2022(actual)
- Construction end
- Apr 9, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 4, 2022
- Construction end13 months lateforecast Mar 1, 2023
Also in Trent Hills
- Construction of the Campbellford Recreation and Wellness Centre$4.1M
- Campbellford Potable Water Supply and Distribution System Upgrades$1.6M
- Replacement of the Hastings Treated Water Standpipe$1.0M
- Installation of Hastings Second Watermain Crossing of Trent River$827.2K
- Watermain Replacement - Hastings$603.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63749 in the federal list. How to read these figures.