North Vancouver - D - Public Electric Vehicle Charging Infrastructure
North Vancouver, British Columbia
Federal contribution
$217,447
Federal share20%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2024
today
20242025202620272028
BuiltForecast
Approved 11 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District of North Vancouver
- Construction start
- Jan 12, 2026(actual)
- Construction end
- Feb 9, 2028(forecast)
Against the original forecast
- Construction start4 weeks lateforecast Dec 15, 2025