12projects·$27.2Mfederal of $56.1M eligible
Strategic Resource Trade Corridors: Bridge and Culvert Rehabilitation
$24.4MChipman +7 · Highways and Roads
underway·approved 2019
New Water Storage Reservoir
$968.7KSt. George · Drinking Water
complete·approved 2015
Construction of a Community Centre
$310.3KSt. George · Recreation
complete·approved 2007
L'Etete Road - Watermain Replacement and New Service Laterals
$263.6KSt. George · Drinking Water
complete·approved 2016
St. George Planning Project - Well Development
$258.0KSt. George · Capacity Building
underway·approved 2022
New Production Well #6 and Preparation Work for Rehabilitation of Well #2
$240.0KSt. George · Drinking Water
complete·approved 2018
Water System Improvements
$195.6KSt. George · Drinking Water
complete·approved 2005
Water and Sanitary Sewer Renewal - Carleton and Portage Street
$176.7KSt. George · Drinking Water
complete·approved 2018
St. George Street Fire Station HVAC - Moncton
$175.8KMoncton · Ventilation
complete·approved 2021
St. George Planning Project - New Lagoon
$102.0KSt. George · Capacity Building
approved·approved 2022
Campbell Hill Road - Watermain Replacement and New Service Laterals
$84.7KSt. George · Drinking Water
complete·approved 2016
Aeration System Upgrade - Lagoon 1
$82.6KSt. George · Wastewater
complete·approved 2018
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Strategic Resource Trade Corridors: Bridge and Culvert Rehabilitation New Brunswick Department of Transportation and Infrastructure | Chipman +7 more | Highways and Roads | underway | $24.4M | $48.8M | 2019 |
| New Water Storage Reservoir Town of St. George | St. George | Drinking Water | complete | $968.7K | $2.9M | 2015 |
| Construction of a Community Centre Town of St. George | St. George | Recreation | complete | $310.3K | $930.9K | 2007 |
| L'Etete Road - Watermain Replacement and New Service Laterals Town of St. George | St. George | Drinking Water | complete | $263.6K | $534.2K | 2016 |
| St. George Planning Project - Well Development Town of St. George | St. George | Capacity Building | underway | $258.0K | $430.0K | 2022 |
| New Production Well #6 and Preparation Work for Rehabilitation of Well #2 Town of St. George | St. George | Drinking Water | complete | $240.0K | $600.0K | 2018 |
| Water System Improvements Town of St. George | St. George | Drinking Water | complete | $195.6K | $586.9K | 2005 |
| Water and Sanitary Sewer Renewal - Carleton and Portage Street Town of St. George | St. George | Drinking Water | complete | $176.7K | $530.1K | 2018 |
| St. George Street Fire Station HVAC - Moncton City of Moncton | Moncton | Ventilation | complete | $175.8K | $250.0K | 2021 |
| St. George Planning Project - New Lagoon Town of St. George | St. George | Capacity Building | approved | $102.0K | $170.0K | 2022 |
| Campbell Hill Road - Watermain Replacement and New Service Laterals Town of St. George | St. George | Drinking Water | complete | $84.7K | $169.3K | 2016 |
| Aeration System Upgrade - Lagoon 1 Town of St. George | St. George | Wastewater | complete | $82.6K | $167.6K | 2018 |