Sewer Separation
Mount Pearl, Newfoundland and Labrador
Federal contribution
$926,452
Federal share41%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Mount Pearl
- Construction start
- Jun 20, 2018(actual)
- Construction end
- Mar 9, 2020(actual)
Against the original forecast
- Construction end4 months lateforecast Oct 31, 2019
Also in Mount Pearl
- Arena and Pool$4.0M
- Commonwealth Avenue Infrastructure Improvements$2.7M
- Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement Farrell Drive (from Holden Street to Evans Place)$2.5M
- Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement Spruce, Birch, Roosevelt Avenues; and Carroll Drive; and Watermain Lining Billard Avenue$2.4M
- Street Improvements$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47082 in the federal list. How to read these figures.