Amber Crescent Culvert Replacement
Federal contribution
$450,000
Federal share50%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Oakville
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Jun 30, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Jan 1, 2017
- Construction end15 months earlyforecast Sep 30, 2021
Also in Oakville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49531 in the federal list. How to read these figures.