Wastewater Inflow and Infiltration Program - Lynn Valley Area
North Vancouver, British Columbia
Federal contribution
$1.8M
$1,760,000
Federal share50%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of North Vancouver
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start11 months earlyforecast Mar 16, 2017
- Construction end3 months lateforecast Dec 31, 2018