Falcon Ridge Water System Improvement
Federal contribution
$362,700
Federal share50%
of $725.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Central Okanagan
- Construction start
- Jul 18, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start6 months earlyforecast Jan 15, 2018
- Construction end3 months earlyforecast Mar 31, 2020
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49770 in the federal list. How to read these figures.