20projects·$10.9Mfederal of $30.1M eligible
Construction of a Multi-Use Health and Wellness Recreation Centre
$6.9MPort Colborne · Sport
complete·approved 2009
Watermain Replacement in Port Colborne
$2.0MPort Colborne · Drinking Water
underway·approved 2022
Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed
$361.7KPort Colborne · Drinking Water
complete·approved 2017
Seaway Wastewater Treatment Plant Aeration Blower Replacement (including surge supression) - located in the City of Port Colbornet
$346.7KNiagara · Wastewater
complete·approved 2017
Seaway Secondary Clarifier Upgrade (Clarifier Gearbox assemblies/scraper arms/drive motor & electrical) - located in the City of Port Colborne
$303.3KNiagara · Wastewater
complete·approved 2017
Catharine Street Watermain
$216.7KPort Colborne · Drinking Water
complete·approved 2009
City of Port Colborne Nickel Beach Bike Lane
$195.2KPort Colborne · Active Transportation
underway·approved 2020
Dain City Multi-Use Trail Improvements
$170.4KPort Colborne · Active Transportation
complete·approved 2021
Carter Street Watermain
$148.0KPort Colborne · Drinking Water
complete·approved 2017
Soccer Complex Restoration and Rehabilitation
$98.7KPort Colborne · Sport
complete·approved 2009
Active Transportation Master Plan for City of Port Colborne Province of Ontario
$50.0KPort Colborne · Capacity Building
complete·approved 2022
City of Port Colborne Constructed Wetland and Walking Trail
$48.8KPort Colborne · Other
approved·approved 2024
Restoration of Sidewalk at Vale Health and Wellness Centre Bus Stop
$21.6KPort Colborne · Public Transit
complete·approved 2017
Restoration of the internal trail system at Thomas A. Lanna Sports Complex (Vale Centre)
$15.0KPort Colborne · Public Transit
complete·approved 2017
Trail Entrance Point Improvements at Various Locations
$15.0KPort Colborne · Active Transportation
complete·approved 2017
Restoration of trail from Robin Hood Mill north to Dain City
$10.0KPort Colborne · Active Transportation
complete·approved 2017
Promenade Improvements on West St south of Clarence St
$10.0KPort Colborne · Public Transit
complete·approved 2017
Restoration of Rrail from Omer Avenue to Weir Road
$7.5KPort Colborne · Active Transportation
complete·approved 2017
Trail Signage Replacements/Improvements/new signage at various locations
$6.9KPort Colborne · Active Transportation
complete·approved 2017
City of Port Colborne Asset Management Program
$6.1KPort Colborne · Capacity Building
complete·approved 2007
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Construction of a Multi-Use Health and Wellness Recreation Centre City of Port Colborne | Port Colborne | Sport | complete | $6.9M | $20.6M | 2009 |
| Watermain Replacement in Port Colborne City of Port Colborne | Port Colborne | Drinking Water | underway | $2.0M | $5.0M | 2022 |
| Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed City of Port Colborne | Port Colborne | Drinking Water | complete | $361.7K | $734.0K | 2017 |
| Seaway Wastewater Treatment Plant Aeration Blower Replacement (including surge supression) - located in the City of Port Colbornet Regional Municipality of Niagara | Niagara | Wastewater | complete | $346.7K | $768.0K | 2017 |
| Seaway Secondary Clarifier Upgrade (Clarifier Gearbox assemblies/scraper arms/drive motor & electrical) - located in the City of Port Colborne Regional Municipality of Niagara | Niagara | Wastewater | complete | $303.3K | $672.0K | 2017 |
| Catharine Street Watermain City of Port Colborne | Port Colborne | Drinking Water | complete | $216.7K | $650.0K | 2009 |
| City of Port Colborne Nickel Beach Bike Lane City of Port Colborne | Port Colborne | Active Transportation | underway | $195.2K | $487.9K | 2020 |
| Dain City Multi-Use Trail Improvements City of Port Colborne | Port Colborne | Active Transportation | complete | $170.4K | $213.0K | 2021 |
| Carter Street Watermain City of Port Colborne | Port Colborne | Drinking Water | complete | $148.0K | $296.0K | 2017 |
| Soccer Complex Restoration and Rehabilitation City of Port Colborne | Port Colborne | Sport | complete | $98.7K | $300.0K | 2009 |
| Active Transportation Master Plan for City of Port Colborne Province of Ontario City of Port Colborne | Port Colborne | Capacity Building | complete | $50.0K | $50.0K | 2022 |
| City of Port Colborne Constructed Wetland and Walking Trail City of Port Colborne | Port Colborne | Other | approved | $48.8K | $140.0K | 2024 |
| Restoration of Sidewalk at Vale Health and Wellness Centre Bus Stop City of Port Colborne | Port Colborne | Public Transit | complete | $21.6K | $48.0K | 2017 |
| Restoration of the internal trail system at Thomas A. Lanna Sports Complex (Vale Centre) City of Port Colborne | Port Colborne | Public Transit | complete | $15.0K | $30.0K | 2017 |
| Trail Entrance Point Improvements at Various Locations City of Port Colborne | Port Colborne | Active Transportation | complete | $15.0K | $30.0K | 2017 |
| Restoration of trail from Robin Hood Mill north to Dain City City of Port Colborne | Port Colborne | Active Transportation | complete | $10.0K | $20.0K | 2017 |
| Promenade Improvements on West St south of Clarence St City of Port Colborne | Port Colborne | Public Transit | complete | $10.0K | $20.0K | 2017 |
| Restoration of Rrail from Omer Avenue to Weir Road City of Port Colborne | Port Colborne | Active Transportation | complete | $7.5K | $15.0K | 2017 |
| Trail Signage Replacements/Improvements/new signage at various locations City of Port Colborne | Port Colborne | Active Transportation | complete | $6.9K | $30.0K | 2017 |
| City of Port Colborne Asset Management Program City of Port Colborne | Port Colborne | Capacity Building | complete | $6.1K | $18.3K | 2007 |