59projects·$612.8Mfederal of $1.7B eligible
Township of Smith-Ennismore-Lakefield - PSAB Preparing for Asset Management
$4.3KPeterborough · Capacity Building
complete·approved 2007
Trail Improvements east of Apsley
$5.8KPeterborough · Recreation
complete·approved 2014
Asset Management
$11.2KPeterborough · Capacity Building
complete·approved 2007
WiFi; Touchless doors, sinks and washrooms; Water Bottle Filling Stations
$18.7KPeterborough · Education, Training and Childcare
complete·approved 2021
Peterborough County Caremobile 2021
$24.0KPeterborough · Public Transit
complete·approved 2020
Asset Management
$24.4KPeterborough · Capacity Building
complete·approved 2007
Replace one accessible Caremobile Van
$38.0KPeterborough · Public Transit
complete·approved 2017
National Survey of School Travel Establishing a travel mode baseline for Canadian communities. Provincial Pilot, Ontario
$50.0KPeterborough · Capacity Building
complete·approved 2022
Trent Master Trail and Active Transportation Plan
$50.0KPeterborough · Capacity Building
approved·approved 2022
Reconstruction of Peterborough County Road 45 Stormwater Collection System
$50.0KPeterborough · Wastewater
complete·approved 2017
Accessible Transit Stop Upgrades of Up to 10-12 New Accessible Transit Stops
$50.0KPeterborough · Public Transit
complete·approved 2017
Limestone trail covering north of Bobcaygeon
$55.2KLindsay +1 · Recreation
complete·approved 2014
COVID 19 Facility and AV Upgrades
$83.5KPeterborough · Administration, Emergency and Public Works
complete·approved 2021
Willow Creek Trail
$120.0KPeterborough · Active Transportation
complete·approved 2009
Peterborough Commuter Rail Engineering Report
$130.7KCavan-Monaghan +8 · Capacity Building
complete·approved 2011
County Road 28 Rehabilitation
$132.6KCavan-Monaghan · Highways and Roads
complete·approved 2010
Specialized Van Expansion
$144.0KPeterborough · Public Transit
underway·approved 2020
Construction of a New Maintenance Facility at Peterborough Airport
$166.7KCavan-Monaghan · Regional And Local Airports
complete·approved 2011
Taylors Bridge Replacement
$195.2KPeterborough · Highways and Roads
complete·approved 2011
Specialized Van Replacement
$237.1KPeterborough · Public Transit
complete·approved 2020
St. Joseph's at Fleming LTCH HVAC Upgrade
$240.0KPeterborough · Ventilation
complete·approved 2021
Transit Storage Garage Replacement Study
$241.7KPeterborough · Public Transit
complete·approved 2017
Rehabilitation of Park Street and Bonaccord Street Bridges
$256.2KPeterborough · Highways and Roads
complete·approved 2006
City Hall (Main Building) Heating, Ventilation and Air Conditionning Replacement
$266.7KPeterborough · Administration, Emergency and Public Works
complete·approved 2011
Replace 5 and Purchase 1 New Accessible Specialized Transit Buses, as part of the Specialized Transit Bus Replacement Program
$337.5KPeterborough · Public Transit
complete·approved 2017
Transit Intelligent Transportation System Enhancements to provide real time passenger information
$350.0KPeterborough · Public Transit
complete·approved 2018
Rotary Greenway Trail Link Lighting and Safety
$390.0KPeterborough · Active Transportation
complete·approved 2022
Replacement of the Mississauga River Bridge
$404.7KBuckhorn · Highways and Roads
complete·approved 2006
Replace Portables Project Group
$480.0KPeterborough · Education, Training and Childcare
complete·approved 2021
HVAC Upgrades and Hands Free Bottle Filling at Various Locations
$600.0KPeterborough · Ventilation
complete·approved 2021
Rehabilitation of Gannons Narrows Bridge and Chases Bridge
$600.0KPeterborough · Highways and Roads
complete·approved 2005
Conventional Bus Refurbishment
$620.0KPeterborough · Public Transit
complete·approved 2020
Reconstruction of County Road 20
$725.3KPeterborough · Highways and Roads
complete·approved 2009
Replacement of Deer Bay Bridge
$788.1KPeterborough · Highways and Roads
complete·approved 2009
Conventional Bus Replacement
$789.1KPeterborough · Public Transit
complete·approved 2020
Highway 115 - Peterborough Road 10 to Highway 7A
$836.0KPeterborough · Highways and Roads
complete·approved 2010
Sports & Wellness Center-Rehabilitation
$843.4KPeterborough · Ventilation
complete·approved 2021
Enhancing Accessibility and Safety at The Mount Community Centre
$846.3KPeterborough · Culture
underway·approved 2021
Transit Stop Upgrades
$920.0KPeterborough · Public Transit
underway·approved 2023
Transit Stop Shelter Upgrades of up to 150 new accessible transit stops and amenities
$1.1MPeterborough · Public Transit
complete·approved 2018
Transit Terminal Upgrades
$1.2MPeterborough · Public Transit
underway·approved 2023
Replace 5 conventional transit buses with new accessible and efficient buses, as part of the Transit Bus Replacement Program
$1.4MPeterborough · Public Transit
complete·approved 2018
Peterborough Bus Extension
$1.5MPeterborough · Public Transit
complete·approved 2020
Construction of a new Transit Maintenance Garage & Public Works Yard
$1.9MPeterborough · Public Transit
complete·approved 2018
Curtis Creek Watershed Flood Reduction Improvements
$2.2MPeterborough · Disaster Mitigation
underway·approved 2022
Upgrade to primary and secondary clarifier tanks and blowers
$2.7MPeterborough · Wastewater
complete·approved 2017
Market Hall Restoration
$2.8MPeterborough · Culture
complete·approved 2011
Conventional Bus Replacement and Refurbishment
$2.9MPeterborough · Public Transit
underway·approved 2023
Rehabilitation of Hunter Street Bridge
$4.4MPeterborough · Highways and Roads
complete·approved 2009
Improvement of the J.A. Gifford Causeway and Yankee Line
$4.8MPeterborough · Highways and Roads
complete·approved 2020
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Township of Smith-Ennismore-Lakefield - PSAB Preparing for Asset Management Township of Smith-Ennismore-Lakefield | Peterborough | Capacity Building | complete | $4.3K | $12.8K | 2007 |
| Trail Improvements east of Apsley Ontario Federation of Snowmobile Clubs: OFSC | Peterborough | Recreation | complete | $5.8K | $11.5K | 2014 |
| Asset Management County of Peterborough | Peterborough | Capacity Building | complete | $11.2K | $33.7K | 2007 |
| WiFi; Touchless doors, sinks and washrooms; Water Bottle Filling Stations Peterborough Victoria Northumberland & Clarington Catholic District School Board | Peterborough | Education, Training and Childcare | complete | $18.7K | $23.4K | 2021 |
| Peterborough County Caremobile 2021 County of Peterborough | Peterborough | Public Transit | complete | $24.0K | $62.9K | 2020 |
| Asset Management City of Peterborough | Peterborough | Capacity Building | complete | $24.4K | $73.3K | 2007 |
| Replace one accessible Caremobile Van County of Peterborough | Peterborough | Public Transit | complete | $38.0K | $100.8K | 2017 |
| National Survey of School Travel Establishing a travel mode baseline for Canadian communities. Provincial Pilot, Ontario Green Communities Association | Peterborough | Capacity Building | complete | $50.0K | $60.0K | 2022 |
| Trent Master Trail and Active Transportation Plan Trent University | Peterborough | Capacity Building | approved | $50.0K | $50.0K | 2022 |
| Reconstruction of Peterborough County Road 45 Stormwater Collection System County of Peterborough | Peterborough | Wastewater | complete | $50.0K | $410.0K | 2017 |
| Accessible Transit Stop Upgrades of Up to 10-12 New Accessible Transit Stops City of Peterborough | Peterborough | Public Transit | complete | $50.0K | $106.2K | 2017 |
| Limestone trail covering north of Bobcaygeon Ontario Federation of Snowmobile Clubs: OFSC | Lindsay +1 more | Recreation | complete | $55.2K | $110.3K | 2014 |
| COVID 19 Facility and AV Upgrades County of Peterborough | Peterborough | Administration, Emergency and Public Works | complete | $83.5K | $104.4K | 2021 |
| Willow Creek Trail City of Peterborough | Peterborough | Active Transportation | complete | $120.0K | $244.4K | 2009 |
| Peterborough Commuter Rail Engineering Report Shining Waters Railway | Cavan-Monaghan +8 more | Capacity Building | complete | $130.7K | $300.0K | 2011 |
| County Road 28 Rehabilitation County of Peterborough | Cavan-Monaghan | Highways and Roads | complete | $132.6K | $400.0K | 2010 |
| Specialized Van Expansion City of Peterborough | Peterborough | Public Transit | underway | $144.0K | $360.0K | 2020 |
| Construction of a New Maintenance Facility at Peterborough Airport City of Peterborough | Cavan-Monaghan | Regional And Local Airports | complete | $166.7K | $500.0K | 2011 |
| Taylors Bridge Replacement County of Peterborough | Peterborough | Highways and Roads | complete | $195.2K | $700.0K | 2011 |
| Specialized Van Replacement City of Peterborough | Peterborough | Public Transit | complete | $237.1K | $592.7K | 2020 |
| St. Joseph's at Fleming LTCH HVAC Upgrade St. Joseph's at Fleming - St. Joseph's at Fleming | Peterborough | Ventilation | complete | $240.0K | $300.0K | 2021 |
| Transit Storage Garage Replacement Study City of Peterborough | Peterborough | Public Transit | complete | $241.7K | $486.0K | 2017 |
| Rehabilitation of Park Street and Bonaccord Street Bridges City of Peterborough | Peterborough | Highways and Roads | complete | $256.2K | $768.6K | 2006 |
| City Hall (Main Building) Heating, Ventilation and Air Conditionning Replacement City of Peterborough | Peterborough | Administration, Emergency and Public Works | complete | $266.7K | $800.0K | 2011 |
| Replace 5 and Purchase 1 New Accessible Specialized Transit Buses, as part of the Specialized Transit Bus Replacement Program City of Peterborough | Peterborough | Public Transit | complete | $337.5K | $675.0K | 2017 |
| Transit Intelligent Transportation System Enhancements to provide real time passenger information City of Peterborough | Peterborough | Public Transit | complete | $350.0K | $700.0K | 2018 |
| Rotary Greenway Trail Link Lighting and Safety City of Peterborough | Peterborough | Active Transportation | complete | $390.0K | $1.5M | 2022 |
| Replacement of the Mississauga River Bridge County of Peterborough | Buckhorn | Highways and Roads | complete | $404.7K | $1.2M | 2006 |
| Replace Portables Project Group Kawartha Pine Ridge District School Board | Peterborough | Education, Training and Childcare | complete | $480.0K | $600.0K | 2021 |
| HVAC Upgrades and Hands Free Bottle Filling at Various Locations Kawartha Pine Ridge District School Board | Peterborough | Ventilation | complete | $600.0K | $750.0K | 2021 |
| Rehabilitation of Gannons Narrows Bridge and Chases Bridge County of Peterborough | Peterborough | Highways and Roads | complete | $600.0K | $1.8M | 2005 |
| Conventional Bus Refurbishment City of Peterborough | Peterborough | Public Transit | complete | $620.0K | $1.2M | 2020 |
| Reconstruction of County Road 20 County of Peterborough | Peterborough | Highways and Roads | complete | $725.3K | $2.2M | 2009 |
| Replacement of Deer Bay Bridge County of Peterborough | Peterborough | Highways and Roads | complete | $788.1K | $2.4M | 2009 |
| Conventional Bus Replacement City of Peterborough | Peterborough | Public Transit | complete | $789.1K | $2.0M | 2020 |
| Highway 115 - Peterborough Road 10 to Highway 7A Government of Ontario | Peterborough | Highways and Roads | complete | $836.0K | $2.5M | 2010 |
| Sports & Wellness Center-Rehabilitation City of Peterborough | Peterborough | Ventilation | complete | $843.4K | $1.1M | 2021 |
| Enhancing Accessibility and Safety at The Mount Community Centre The Mount Community Centre | Peterborough | Culture | underway | $846.3K | $2.1M | 2021 |
| Transit Stop Upgrades City of Peterborough | Peterborough | Public Transit | underway | $920.0K | $2.3M | 2023 |
| Transit Stop Shelter Upgrades of up to 150 new accessible transit stops and amenities City of Peterborough | Peterborough | Public Transit | complete | $1.1M | $2.2M | 2018 |
| Transit Terminal Upgrades City of Peterborough | Peterborough | Public Transit | underway | $1.2M | $3.0M | 2023 |
| Replace 5 conventional transit buses with new accessible and efficient buses, as part of the Transit Bus Replacement Program City of Peterborough | Peterborough | Public Transit | complete | $1.4M | $2.9M | 2018 |
| Peterborough Bus Extension City of Peterborough | Peterborough | Public Transit | complete | $1.5M | $3.8M | 2020 |
| Construction of a new Transit Maintenance Garage & Public Works Yard City of Peterborough | Peterborough | Public Transit | complete | $1.9M | $5.7M | 2018 |
| Curtis Creek Watershed Flood Reduction Improvements City of Peterborough | Peterborough | Disaster Mitigation | underway | $2.2M | $5.4M | 2022 |
| Upgrade to primary and secondary clarifier tanks and blowers City of Peterborough | Peterborough | Wastewater | complete | $2.7M | $5.4M | 2017 |
| Market Hall Restoration City of Peterborough | Peterborough | Culture | complete | $2.8M | $8.4M | 2011 |
| Conventional Bus Replacement and Refurbishment City of Peterborough | Peterborough | Public Transit | underway | $2.9M | $7.7M | 2023 |
| Rehabilitation of Hunter Street Bridge City of Peterborough | Peterborough | Highways and Roads | complete | $4.4M | $13.1M | 2009 |
| Improvement of the J.A. Gifford Causeway and Yankee Line County of Peterborough | Peterborough | Highways and Roads | complete | $4.8M | $9.6M | 2020 |