89projects·$95.8Mfederal of $246.5M eligible
Installation of New Bike Racks for Business
$10.0KThunder Bay · Active Transportation
complete·approved 2017
Post Assessment Repairs to Stormwater Outfalls
$12.5KThunder Bay · Wastewater
complete·approved 2017
Construction of Low Impact Development Stormwater Management Facilities in the McVicar Creek Basin
$14.0KThunder Bay · Wastewater
complete·approved 2017
Construction of Pedestrian Crossover
$18.6KThunder Bay · Public Transit
complete·approved 2017
Construction of a 300mm Stormwater Separation Sewer on McGillivray Street
$22.0KThunder Bay · Wastewater
complete·approved 2017
Extension of Catch Basins in Multiple Locations to Improve Local Drainage
$25.0KThunder Bay · Wastewater
complete·approved 2017
Storm Sewer Replacement on Egan Street - Algoma Street to Garrard Street
$25.0KThunder Bay · Wastewater
complete·approved 2017
First Avenue Drainage Improvements including Design and Construction of 150m of Storm Sewer
$25.1KThunder Bay · Wastewater
complete·approved 2018
Frederica Street Active Living Corridor - Sidewalk Connection
$27.0KThunder Bay · Public Transit
complete·approved 2017
Smart Card Electronic Fare Technology Feasibility Study (Phase I)
$27.7KThunder Bay · Public Transit
complete·approved 2017
City of Thunder Bay Asset Management
$35.5KThunder Bay · Capacity Building
complete·approved 2007
Sandy Beach Road Ditch Upgrade and Deepening
$40.1KThunder Bay · Wastewater
complete·approved 2018
Construction of Pedestrian Crossover
$48.0KThunder Bay · Public Transit
complete·approved 2017
Hilldale Road and Trendiak Road Culvert Replacement Program
$50.0KThunder Bay · Wastewater
complete·approved 2017
Lyon Ditch Drainage Improvements including Increased Capacity
$50.0KThunder Bay · Wastewater
complete·approved 2017
Replacement of Sanitary Sewer connections on First Avenue: Memorial Avenue to Fort William Road
$50.0KThunder Bay · Wastewater
complete·approved 2017
Enhanced Pedestrian Walkway on Arthur St.
$55.0KThunder Bay · Public Transit
complete·approved 2017
Construction of New Bike Lane
$55.0KThunder Bay · Active Transportation
complete·approved 2017
Design of Comprehensive Surface/Stormwater Management Plan for the Solid Waste and Recycling Facility
$56.7KThunder Bay · Wastewater
complete·approved 2017
Construction of 375-450mm Stormwater Separation Sewer on Selkirk Street - Arthur Street to Cuthbertson Place and Cuthbertson Place - Selkirk St to Franklin St.
$57.9KThunder Bay · Wastewater
complete·approved 2018
Replacement/Updating of Bus Stop Signage and Route Wayfinding Signage
$60.0KThunder Bay · Public Transit
complete·approved 2017
Drainage improvements and Low Impact Development at Birch Point
$60.3KThunder Bay · Wastewater
complete·approved 2018
Storm Sewer Installation on Crescent Avenue - Cox Crescent to 80 m N
$61.1KThunder Bay · Wastewater
complete·approved 2018
Highgate Road Drainage Improvements Including Design and Construction
$67.2KThunder Bay · Wastewater
complete·approved 2017
Construction of a 375mm Storm Sewer on Burris Street - Margaret Street to 100 m north - to Address Local Surface Drainage Issues
$76.3KThunder Bay · Wastewater
complete·approved 2018
New Secondary Access to Maintenance Facility and Upgrades
$80.0KThunder Bay · Public Transit
underway·approved 2023
City-Wide Stormwater Infrastructure Inventory and Condition Assessment
$80.2KThunder Bay · Wastewater
complete·approved 2018
Replacement of Controller Vehicles
$82.4KThunder Bay · Public Transit
complete·approved 2022
Construction of 450mm Stormwater Separation Sewer on Murray Avenue - Franklin Street to Selkirk Street
$87.6KThunder Bay · Wastewater
complete·approved 2018
Construct Low Impact Development Stormwater Management Facility within George Burke Park
$92.6KThunder Bay · Wastewater
complete·approved 2018
Construction of 450mm Stormwater Separation Sewer on Isabella Street - Franklin Street to Selkirk Street
$96.5KThunder Bay · Wastewater
complete·approved 2018
Pedestrian Wayfinding Signage
$100.0KThunder Bay · Public Transit
complete·approved 2017
Windsor Street Active Living Corridor - Sidewalk Connection
$103.3KThunder Bay · Public Transit
complete·approved 2017
Replacement of Transit Bus Hoist
$110.0KThunder Bay · Public Transit
complete·approved 2017
Transit Fleet Service Equipment
$111.3KThunder Bay · Public Transit
complete·approved 2020
Construction of 1500mm Stormwater Outfall at James Street - Neebing River to Riverview Drive
$125.0KThunder Bay · Wastewater
complete·approved 2017
Construction of a 450-525 mm Relief Storm Sewer from McGill Crescent to the Dalhousie / McMaster St. Area
$125.0KThunder Bay · Wastewater
complete·approved 2017
ITS/Software Improvement - New On Demand Mobility Management Software Modules
$126.0KThunder Bay · Public Transit
underway·approved 2020
City of Thunder Bay-Planning- Feasibility Study and Fleet Transition Plan
$128.4KThunder Bay · Capacity Building
complete·approved 2022
Study for New Centralized Transit Terminal & Route Network Implementation (Phase I)
$149.8KThunder Bay · Public Transit
complete·approved 2017
Pioneer Ridge - HVAC System Ventilation Improvements
$153.5KThunder Bay · Ventilation
complete·approved 2023
Thunder Bay Transit - Specialized Fleet Expansion
$157.7KThunder Bay · Public Transit
complete·approved 2020
Accessible Bus Stop Improvements & Shelter Upgrades at multiple bus stops
$164.3KThunder Bay · Public Transit
complete·approved 2017
Mobility Systems Hardware
$179.6KThunder Bay · Public Transit
complete·approved 2020
HVAC-Retro Fit Resident Rooms with Cooling and Ultraviolet Lamps
$186.4KThunder Bay · Ventilation
complete·approved 2021
600 mm Storm Sewer Installation on Frederica Street - W Neebing to Dead End
$200.0KThunder Bay · Wastewater
complete·approved 2018
Rehabilitation and upgrading to City Hall Transit Hub infrastructure
$200.0KThunder Bay · Public Transit
complete·approved 2017
Conduct Hydraulic Engineering Drainage Study in the Intercity Area
$200.2KThunder Bay · Wastewater
complete·approved 2018
Construction of a 1200mm Storm Sewer from the McIntyre River to Balmoral St and north to John St
$202.5KThunder Bay · Wastewater
complete·approved 2017
Signalized Bus Priority
$210.0KThunder Bay · Public Transit
approved·approved 2023
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Installation of New Bike Racks for Business Corporation of the City of Thunder Bay | Thunder Bay | Active Transportation | complete | $10.0K | $20.0K | 2017 |
| Post Assessment Repairs to Stormwater Outfalls Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $12.5K | $25.0K | 2017 |
| Construction of Low Impact Development Stormwater Management Facilities in the McVicar Creek Basin Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $14.0K | $52.0K | 2017 |
| Construction of Pedestrian Crossover Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $18.6K | $50.0K | 2017 |
| Construction of a 300mm Stormwater Separation Sewer on McGillivray Street Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $22.0K | $44.0K | 2017 |
| Extension of Catch Basins in Multiple Locations to Improve Local Drainage Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $25.0K | $50.0K | 2017 |
| Storm Sewer Replacement on Egan Street - Algoma Street to Garrard Street Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $25.0K | $50.0K | 2017 |
| First Avenue Drainage Improvements including Design and Construction of 150m of Storm Sewer Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $25.1K | $50.2K | 2018 |
| Frederica Street Active Living Corridor - Sidewalk Connection Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $27.0K | $54.0K | 2017 |
| Smart Card Electronic Fare Technology Feasibility Study (Phase I) Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $27.7K | $130.0K | 2017 |
| City of Thunder Bay Asset Management City of Thunder Bay | Thunder Bay | Capacity Building | complete | $35.5K | $106.5K | 2007 |
| Sandy Beach Road Ditch Upgrade and Deepening Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $40.1K | $80.3K | 2018 |
| Construction of Pedestrian Crossover Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $48.0K | $100.0K | 2017 |
| Hilldale Road and Trendiak Road Culvert Replacement Program Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $50.0K | $100.0K | 2017 |
| Lyon Ditch Drainage Improvements including Increased Capacity Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $50.0K | $100.0K | 2017 |
| Replacement of Sanitary Sewer connections on First Avenue: Memorial Avenue to Fort William Road Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $50.0K | $100.0K | 2017 |
| Enhanced Pedestrian Walkway on Arthur St. Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $55.0K | $110.0K | 2017 |
| Construction of New Bike Lane Corporation of the City of Thunder Bay | Thunder Bay | Active Transportation | complete | $55.0K | $110.0K | 2017 |
| Design of Comprehensive Surface/Stormwater Management Plan for the Solid Waste and Recycling Facility Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $56.7K | $150.0K | 2017 |
| Construction of 375-450mm Stormwater Separation Sewer on Selkirk Street - Arthur Street to Cuthbertson Place and Cuthbertson Place - Selkirk St to Franklin St. Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $57.9K | $115.8K | 2018 |
| Replacement/Updating of Bus Stop Signage and Route Wayfinding Signage Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $60.0K | $120.0K | 2017 |
| Drainage improvements and Low Impact Development at Birch Point Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $60.3K | $120.6K | 2018 |
| Storm Sewer Installation on Crescent Avenue - Cox Crescent to 80 m N Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $61.1K | $122.1K | 2018 |
| Highgate Road Drainage Improvements Including Design and Construction Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $67.2K | $150.0K | 2017 |
| Construction of a 375mm Storm Sewer on Burris Street - Margaret Street to 100 m north - to Address Local Surface Drainage Issues Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $76.3K | $152.5K | 2018 |
| New Secondary Access to Maintenance Facility and Upgrades Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | underway | $80.0K | $200.0K | 2023 |
| City-Wide Stormwater Infrastructure Inventory and Condition Assessment Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $80.2K | $160.4K | 2018 |
| Replacement of Controller Vehicles Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $82.4K | $205.9K | 2022 |
| Construction of 450mm Stormwater Separation Sewer on Murray Avenue - Franklin Street to Selkirk Street Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $87.6K | $175.2K | 2018 |
| Construct Low Impact Development Stormwater Management Facility within George Burke Park Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $92.6K | $285.0K | 2018 |
| Construction of 450mm Stormwater Separation Sewer on Isabella Street - Franklin Street to Selkirk Street Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $96.5K | $192.9K | 2018 |
| Pedestrian Wayfinding Signage Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Windsor Street Active Living Corridor - Sidewalk Connection Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $103.3K | $206.5K | 2017 |
| Replacement of Transit Bus Hoist Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $110.0K | $220.0K | 2017 |
| Transit Fleet Service Equipment Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $111.3K | $278.3K | 2020 |
| Construction of 1500mm Stormwater Outfall at James Street - Neebing River to Riverview Drive Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $125.0K | $250.0K | 2017 |
| Construction of a 450-525 mm Relief Storm Sewer from McGill Crescent to the Dalhousie / McMaster St. Area Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $125.0K | $250.0K | 2017 |
| ITS/Software Improvement - New On Demand Mobility Management Software Modules Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | underway | $126.0K | $315.0K | 2020 |
| City of Thunder Bay-Planning- Feasibility Study and Fleet Transition Plan Corporation of the City of Thunder Bay | Thunder Bay | Capacity Building | complete | $128.4K | $160.5K | 2022 |
| Study for New Centralized Transit Terminal & Route Network Implementation (Phase I) Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $149.8K | $300.0K | 2017 |
| Pioneer Ridge - HVAC System Ventilation Improvements The Corporation of the City of Thunder Bay - Pioneer Ridge | Thunder Bay | Ventilation | complete | $153.5K | $191.9K | 2023 |
| Thunder Bay Transit - Specialized Fleet Expansion Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $157.7K | $394.3K | 2020 |
| Accessible Bus Stop Improvements & Shelter Upgrades at multiple bus stops Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $164.3K | $340.0K | 2017 |
| Mobility Systems Hardware Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $179.6K | $449.1K | 2020 |
| HVAC-Retro Fit Resident Rooms with Cooling and Ultraviolet Lamps The Corporation of the City of Thunder Bay - Pioneer Ridge | Thunder Bay | Ventilation | complete | $186.4K | $224.0K | 2021 |
| 600 mm Storm Sewer Installation on Frederica Street - W Neebing to Dead End Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $200.0K | $400.0K | 2018 |
| Rehabilitation and upgrading to City Hall Transit Hub infrastructure Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $200.0K | $400.0K | 2017 |
| Conduct Hydraulic Engineering Drainage Study in the Intercity Area Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $200.2K | $427.7K | 2018 |
| Construction of a 1200mm Storm Sewer from the McIntyre River to Balmoral St and north to John St Corporation of the City of Thunder Bay | Thunder Bay | Wastewater | complete | $202.5K | $405.0K | 2017 |
| Signalized Bus Priority Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | approved | $210.0K | $525.0K | 2023 |