2,320projects·$1.8Bfederal of $3.8B eligible
Addition of standby filter cartridge housing for Alpine Water treatment plant
$3.8KTrent Lakes · Drinking Water
complete·approved 2017
Trenchless Technology for Multiple Storm Sewer Pipes and Rebuild of Deteriorating Structures County Road 73 in Deep River
$3.8KRenfrew · Wastewater
complete·approved 2017
Upgrade Pump at Sewage Lift Station #2
$4.0KPowassan · Wastewater
complete·approved 2017
Purchase and Install 2 of the 3 raw water low lift pumps at 50 Agnes Street, Charlton
$4.0KCharlton and Dack · Drinking Water
complete·approved 2017
Upgrade culverts, Ditching Guild Rd. 20 homes
$4.0KFront of Yonge · Wastewater
complete·approved 2017
Upgrade Ditches, drainage, Lake Street 70+ homes
$4.0KFront of Yonge · Wastewater
complete·approved 2017
Replacement of Road Crossing Culvert on County Road 10, Close to Civic Address 5444
$4.0KPrescott and Russell · Wastewater
complete·approved 2017
Restoration of stormdrain outfall
$4.0KChippewas of Rama First Nation≈ · Wastewater
complete·approved 2017
Replacement of Culverts/Ditching on Salmon Side Road
$4.1KRideau Lakes · Wastewater
complete·approved 2018
Purchase and installation of remote chlorine analyzer(s) in the distribution system
$4.2KShawanaga First Nation · Drinking Water
complete·approved 2017
Rehabilitation of the Village Lift Station
$4.2KOneida Nation of the Thames≈ · Wastewater
complete·approved 2017
Replacement of 35 year old Pump at Well Building
$4.3KGogama · Drinking Water
complete·approved 2017
Undertake smoke tests on wastewater network to assess and address overflow problems at the lagoon
$4.3KVal Rita-Harty · Wastewater
complete·approved 2017
Southwest Middlesex Graham Road Pumping Station/Reservoir Upgrade
$4.4KSouthwest Middlesex · Drinking Water
complete·approved 2017
Upgrade Ditches, drainage, Junetown Rd.35 homes
$4.5KFront of Yonge · Wastewater
complete·approved 2017
Recalibration of the Curve Lake Pump House
$4.5KCurve Lake First Nation · Drinking Water
complete·approved 2017
Radio Communication System for Raw Water Pumping Station
$4.6KHornepayne · Drinking Water
complete·approved 2017
Replacement of road crossing culvert on County Road 24, close to civic address 2515
$4.8KPrescott and Russell · Wastewater
complete·approved 2017
Broken hydrant replacement near 1 Koval Street and upgrading approximately 30 metres of water main to prevent future freeze-ups.
$4.9KPickle Lake · Wastewater
complete·approved 2017
Lagoon inlet pipe/valve replacement
$5.0KSeine River First Nation · Wastewater
complete·approved 2017
Design needed for the separation of the drinking water and the sewer line as the water line is crossing the sewer line. (phase 1 of 2)
$5.0KMcGarry · Wastewater
complete·approved 2017
Wastewater Lagoon Cells Clean Up
$5.0KGogama · Wastewater
complete·approved 2017
Water Treatment 1 - Chlorine System Rehabilitation
$5.0KChippewas of the Thames First Nation≈ · Drinking Water
complete·approved 2017
Interconnectivity valve replacement between clear wells
$5.0KOpasatika · Drinking Water
complete·approved 2017
Rehabilitation of Booster Station at Evan John/ Oneida Roads Intersection
$5.0KOneida Nation of the Thames≈ · Drinking Water
complete·approved 2017
Replacement of 9th Concession Road Culvert
$5.1KRideau Lakes · Wastewater
complete·approved 2018
Preliminary Design of a Standalone Water Treatment System for the Administration Office and Community Centre to Meet Guidelines and Remove Health and Safety Risks
$5.2KWahta Mohawks≈ · Drinking Water
complete·approved 2017
Environmental Risk Assessment for Lagoon
$5.2KSaint-Hilaire · Capacity Building
complete·approved 2016
Equipment Upgrades at Water Treatment Plant
$5.2KAnishinaabeg of Naongashiing≈ · Drinking Water
complete·approved 2017
Heenan Place Sanitary Sewer Relining - Narin Westerly
$5.2KKenora · Wastewater
complete·approved 2017
Rehabilitation of sewage pumps #1 and #2 at Pumping Station #2
$5.3KNorth Stormont · Wastewater
complete·approved 2017
Replacement of road crossing culvert on County Road 4 at the intersection of Golf Road
$5.3KPrescott and Russell · Wastewater
complete·approved 2017
Leclerc Lift Station Cancellation and Looping Study
$5.6KGrand Falls · Capacity Building
complete·approved 2016
Major Pre-Cleaning and Closed-Circuit Television (CCTV) Condition Assessment of Wastewater Sewers in Atironto
$5.7KMontague · Wastewater
complete·approved 2017
Monitoring Equipment Upgrades at Water Distribution/Generator Building
$5.8KGogama · Drinking Water
complete·approved 2017
Waterproof existing valve chamber on raw water main
$5.8KGeorgian Bluffs · Drinking Water
complete·approved 2017
Wastewater Feasibility Study for Community Lot Servicing
$6.0KAamjiwnaang First Nation≈ · Wastewater
complete·approved 2017
Repair programmable logic controller (PLC) at the water treatment plant. Located at the Elk Lake water Treatment plant, 4 First Street which serves 440 residents and 160 service connections.
$6.0KJames · Drinking Water
complete·approved 2017
Margaret Street Culvert Rehabilitation
$6.0KNeebing · Wastewater
complete·approved 2018
Addition of Backflow Preventers at Fifth St. Sewage Pumping Station
$6.1KHearst · Wastewater
complete·approved 2018
Replacement of Cliff Road Culvert
$6.1KRideau Lakes · Wastewater
complete·approved 2018
Installation of New 15 Horsepower Primary Well Pump
$6.1KHilton Beach · Drinking Water
complete·approved 2017
Install a backup generator for the water treatment facility
$6.1KThessalon First Nation · Drinking Water
complete·approved 2017
Bulk Water Upgrades
$6.1KMossey River · Drinking Water
complete·approved 2017
Replacement of corroded soda ash tank system with a new poly tank and stainless feeder at the Nairn Centre Water Treatment Plant
$6.2KNairn and Hyman · Drinking Water
complete·approved 2017
Repairs and upgrades at Sewage Pumping Station
$6.3KAttawapiskat First Nation · Wastewater
complete·approved 2017
Stormwater Drainage Study
$6.3KAamjiwnaang First Nation≈ · Wastewater
complete·approved 2017
Replacement of two well pumps at the Crysler Well Heads
$6.3KNorth Stormont · Drinking Water
complete·approved 2017
Chlorination/PRV Building Upgrade
$6.3KSouth River · Drinking Water
complete·approved 2016
Replacement of roofing on Church Road Pumping Station Building
$6.4KArmstrong · Wastewater
complete·approved 2018
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Addition of standby filter cartridge housing for Alpine Water treatment plant Municipality of Trent Lakes | Trent Lakes | Drinking Water | complete | $3.8K | $7.5K | 2017 |
| Trenchless Technology for Multiple Storm Sewer Pipes and Rebuild of Deteriorating Structures County Road 73 in Deep River County of Renfrew | Renfrew | Wastewater | complete | $3.8K | $20.0K | 2017 |
| Upgrade Pump at Sewage Lift Station #2 Municipality of Powassan | Powassan | Wastewater | complete | $4.0K | $8.0K | 2017 |
| Purchase and Install 2 of the 3 raw water low lift pumps at 50 Agnes Street, Charlton Municipality of Charlton and Dack | Charlton and Dack | Drinking Water | complete | $4.0K | $8.0K | 2017 |
| Upgrade culverts, Ditching Guild Rd. 20 homes Township of Front of Yonge | Front of Yonge | Wastewater | complete | $4.0K | $8.0K | 2017 |
| Upgrade Ditches, drainage, Lake Street 70+ homes Township of Front of Yonge | Front of Yonge | Wastewater | complete | $4.0K | $8.0K | 2017 |
| Replacement of Road Crossing Culvert on County Road 10, Close to Civic Address 5444 United Counties of Prescott and Russell | Prescott and Russell | Wastewater | complete | $4.0K | $9.0K | 2017 |
| Restoration of stormdrain outfall Chippewas of Rama First Nation | Chippewas of Rama First Nation≈ | Wastewater | complete | $4.0K | $12.0K | 2017 |
| Replacement of Culverts/Ditching on Salmon Side Road Township of Rideau Lakes | Rideau Lakes | Wastewater | complete | $4.1K | $8.2K | 2018 |
| Purchase and installation of remote chlorine analyzer(s) in the distribution system Shawanaga First Nation | Shawanaga First Nation | Drinking Water | complete | $4.2K | $12.0K | 2017 |
| Rehabilitation of the Village Lift Station Oneida Nation of the Thames | Oneida Nation of the Thames≈ | Wastewater | complete | $4.2K | $30.1K | 2017 |
| Replacement of 35 year old Pump at Well Building Local Services Board of Gogama | Gogama | Drinking Water | complete | $4.3K | $8.5K | 2017 |
| Undertake smoke tests on wastewater network to assess and address overflow problems at the lagoon Township of Val Rita-Harty | Val Rita-Harty | Wastewater | complete | $4.3K | $8.5K | 2017 |
| Southwest Middlesex Graham Road Pumping Station/Reservoir Upgrade Municipality of Southwest Middlesex | Southwest Middlesex | Drinking Water | complete | $4.4K | $10.4K | 2017 |
| Upgrade Ditches, drainage, Junetown Rd.35 homes Township of Front of Yonge | Front of Yonge | Wastewater | complete | $4.5K | $9.0K | 2017 |
| Recalibration of the Curve Lake Pump House Curve Lake First Nation | Curve Lake First Nation | Drinking Water | complete | $4.5K | $18.0K | 2017 |
| Radio Communication System for Raw Water Pumping Station Township of Hornepayne | Hornepayne | Drinking Water | complete | $4.6K | $10.0K | 2017 |
| Replacement of road crossing culvert on County Road 24, close to civic address 2515 United Counties of Prescott and Russell | Prescott and Russell | Wastewater | complete | $4.8K | $9.5K | 2017 |
| Broken hydrant replacement near 1 Koval Street and upgrading approximately 30 metres of water main to prevent future freeze-ups. Township of Pickle Lake | Pickle Lake | Wastewater | complete | $4.9K | $38.1K | 2017 |
| Lagoon inlet pipe/valve replacement Seine River First Nation | Seine River First Nation | Wastewater | complete | $5.0K | $10.0K | 2017 |
| Design needed for the separation of the drinking water and the sewer line as the water line is crossing the sewer line. (phase 1 of 2) Township of McGarry | McGarry | Wastewater | complete | $5.0K | $10.0K | 2017 |
| Wastewater Lagoon Cells Clean Up Local Services Board of Gogama | Gogama | Wastewater | complete | $5.0K | $10.0K | 2017 |
| Water Treatment 1 - Chlorine System Rehabilitation Chippewas of the Thames First Nation | Chippewas of the Thames First Nation≈ | Drinking Water | complete | $5.0K | $10.0K | 2017 |
| Interconnectivity valve replacement between clear wells Township of Opasatika | Opasatika | Drinking Water | complete | $5.0K | $10.0K | 2017 |
| Rehabilitation of Booster Station at Evan John/ Oneida Roads Intersection Oneida Nation of the Thames | Oneida Nation of the Thames≈ | Drinking Water | complete | $5.0K | $10.1K | 2017 |
| Replacement of 9th Concession Road Culvert Township of Rideau Lakes | Rideau Lakes | Wastewater | complete | $5.1K | $10.1K | 2018 |
| Preliminary Design of a Standalone Water Treatment System for the Administration Office and Community Centre to Meet Guidelines and Remove Health and Safety Risks Wahta Mohawks | Wahta Mohawks≈ | Drinking Water | complete | $5.2K | $10.3K | 2017 |
| Environmental Risk Assessment for Lagoon Village of Saint-Hilaire | Saint-Hilaire | Capacity Building | complete | $5.2K | $11.4K | 2016 |
| Equipment Upgrades at Water Treatment Plant Anishinaabeg of Naongashiing | Anishinaabeg of Naongashiing≈ | Drinking Water | complete | $5.2K | $79.0K | 2017 |
| Heenan Place Sanitary Sewer Relining - Narin Westerly City of Kenora | Kenora | Wastewater | complete | $5.2K | $10.5K | 2017 |
| Rehabilitation of sewage pumps #1 and #2 at Pumping Station #2 Township of North Stormont | North Stormont | Wastewater | complete | $5.3K | $10.5K | 2017 |
| Replacement of road crossing culvert on County Road 4 at the intersection of Golf Road United Counties of Prescott and Russell | Prescott and Russell | Wastewater | complete | $5.3K | $10.7K | 2017 |
| Leclerc Lift Station Cancellation and Looping Study Grand Falls Regional Municipality | Grand Falls | Capacity Building | complete | $5.6K | $36.5K | 2016 |
| Major Pre-Cleaning and Closed-Circuit Television (CCTV) Condition Assessment of Wastewater Sewers in Atironto Township of Montague | Montague | Wastewater | complete | $5.7K | $14.0K | 2017 |
| Monitoring Equipment Upgrades at Water Distribution/Generator Building Local Services Board of Gogama | Gogama | Drinking Water | complete | $5.8K | $11.5K | 2017 |
| Waterproof existing valve chamber on raw water main Township of Georgian Bluffs | Georgian Bluffs | Drinking Water | complete | $5.8K | $20.0K | 2017 |
| Wastewater Feasibility Study for Community Lot Servicing Aamjiwnaang First Nation | Aamjiwnaang First Nation≈ | Wastewater | complete | $6.0K | $40.0K | 2017 |
| Repair programmable logic controller (PLC) at the water treatment plant. Located at the Elk Lake water Treatment plant, 4 First Street which serves 440 residents and 160 service connections. Township of James | James | Drinking Water | complete | $6.0K | $12.2K | 2017 |
| Margaret Street Culvert Rehabilitation Municipality of Neebing | Neebing | Wastewater | complete | $6.0K | $12.0K | 2018 |
| Addition of Backflow Preventers at Fifth St. Sewage Pumping Station Corporation of the Town of Hearst | Hearst | Wastewater | complete | $6.1K | $12.5K | 2018 |
| Replacement of Cliff Road Culvert Township of Rideau Lakes | Rideau Lakes | Wastewater | complete | $6.1K | $12.2K | 2018 |
| Installation of New 15 Horsepower Primary Well Pump Village of Hilton Beach | Hilton Beach | Drinking Water | complete | $6.1K | $12.2K | 2017 |
| Install a backup generator for the water treatment facility Thessalon First Nation | Thessalon First Nation | Drinking Water | complete | $6.1K | $12.3K | 2017 |
| Bulk Water Upgrades Rural Municipality of Mossey River | Mossey River | Drinking Water | complete | $6.1K | $15.0K | 2017 |
| Replacement of corroded soda ash tank system with a new poly tank and stainless feeder at the Nairn Centre Water Treatment Plant Township of Nairn and Hyman | Nairn and Hyman | Drinking Water | complete | $6.2K | $12.4K | 2017 |
| Repairs and upgrades at Sewage Pumping Station Attawapiskat First Nation | Attawapiskat First Nation | Wastewater | complete | $6.3K | $12.5K | 2017 |
| Stormwater Drainage Study Aamjiwnaang First Nation | Aamjiwnaang First Nation≈ | Wastewater | complete | $6.3K | $40.0K | 2017 |
| Replacement of two well pumps at the Crysler Well Heads Township of North Stormont | North Stormont | Drinking Water | complete | $6.3K | $12.5K | 2017 |
| Chlorination/PRV Building Upgrade Town of South River | South River | Drinking Water | complete | $6.3K | $42.4K | 2016 |
| Replacement of roofing on Church Road Pumping Station Building Township of Armstrong | Armstrong | Wastewater | complete | $6.4K | $12.8K | 2018 |