20,506projects·$69.4Bfederal of $184.8B eligible
Municipality of Chatham-Kent - Planning - Feasibility Study and Fleet Transition Plan
$100.4KChatham-Kent · Capacity Building
complete·approved 2022
Grid Road Reconstruction
$100.3KReward · Highways and Roads
complete·approved 2006
Rivervale and Oasis Sewer Service Pump Replacements
$100.3KKootenay Boundary · Wastewater
complete·approved 2017
Pump house and Water Intake Upgrades
$100.2KBaie Verte · Drinking Water
complete·approved 2020
Auxilary Power for the Town's Wastewater Treatment
$100.1KStewiacke · Wastewater
complete·approved 2016
Design and Construction of Graham Creek Stormwater Measures
$100.1KOttawa · Wastewater
complete·approved 2017
Accessible Woodland Trail Construction
$100.1KNorthumberland · Active Transportation
complete·approved 2021
Service improvement plan
$100.1KLongueuil · Public Transit
complete·approved 2017
New Sewage Lift Station No.3
$100.0KCarrot River · Wastewater
complete·approved 2009
Relocation of the Downtown Terminal
$100.0KSault Ste. Marie · Public Transit
complete·approved 2020
Kings Transit Authority - Phase 1 - Planning Study for Electrification of Transit
$100.0KKings · Capacity Building
underway·approved 2022
Caboto Centre Upgrades
$100.0KWinnipeg · Recreation
complete·approved 2022
The Villa LTC Home Chiller Upgrade
$100.0KLambton · Ventilation
complete·approved 2021
Creation of 2 pressurized neonatal rooms in the Maisonneuve pavilion (7th floor, D wing)
$100.0KMontréal · Ventilation
complete·approved 2021
Caraquet - Regional Generations Centre (Phase 1)
$100.0KCaraquet · Capacity Building
complete·approved 2020
Central Kootenay - Galena Trail Restoration
$100.0KCentral Kootenay Regional District - Electoral H≈ · Active Transportation
complete·approved 2020
Replacement of Bus Shelters
$100.0KSault Ste. Marie · Public Transit
complete·approved 2020
Municipality of the County of Richmond - Arichat Water Treatment Plant Upgrades
$100.0KRichmond · Drinking Water
complete·approved 2019
LED Lighting Upgrades at Approximately 42 Wastewater Pumping Stations Across the City
$100.0KOttawa · Wastewater
complete·approved 2018
West Side Pond Rehabilitation and Sediment Cleanout
$100.0KClarington · Wastewater
complete·approved 2018
Separation of sewers on Lorne/Gladstone/Melrose/Henry/William Avenues
$100.0KLeamington · Wastewater
complete·approved 2018
Quantification of ridership through the use of automatic passenger counters
$100.0KWindsor · Public Transit
complete·approved 2017
Installation of 60 Pedestrian Countdown Signal Heads
$100.0KLondon · Public Transit
complete·approved 2017
Saskatchewan Highway Water and Sewer Renewal
$100.0KWestLake-Gladstone≈ · Drinking Water
complete·approved 2017
Oil City/Oil Springs Reservoir Upgrades
$100.0KOil Springs · Drinking Water
complete·approved 2017
Replace 15 Main Valves Within the Water Distribution System
$100.0KHornepayne · Drinking Water
complete·approved 2017
Assessment, Construction and Implementation of a Drinking Water System Dead-End Looping Strategy in the Central Pressure Zone
$100.0KNewmarket · Drinking Water
complete·approved 2017
Replace existing water treatment control system at all three facilities to extend asset life through online asset management
$100.0KMono · Drinking Water
complete·approved 2017
Thornbury Wastewater Treatment Plant Roof and Heating, Ventilation and Air Conditioning (HVAC) Replacement
$100.0KThe Blue Mountains · Wastewater
complete·approved 2017
Replacement of Maple Street Storm Sewer - Replacing 110m of storm sewer between Maple St. & McKay Crt.
$100.0KCollingwood · Wastewater
complete·approved 2017
Village of Sombra Main Pumping Station Rehabilitation
$100.0KSt. Clair · Wastewater
complete·approved 2017
Village of Port Lambton Main Pumping Station Rehabilitation
$100.0KSt. Clair · Wastewater
complete·approved 2017
Sanitary Sewer Trenchless Repairs (Township Wide Backlog)
$100.0KSt. Clair · Wastewater
complete·approved 2017
Brighton Street new storm sewer from Garnet Street to Facer Street
$100.0KSt. Catharines · Wastewater
complete·approved 2017
Structural relining of 300mm watermain at the Flora Street river crossing.
$100.0KCarleton Place · Drinking Water
complete·approved 2017
Water Treatment Plant and Reservoir Upgrade
$100.0KMossbank · Drinking Water
complete·approved 2017
Water Supply System Pipeline Upgrade
$100.0KEnglefeld · Drinking Water
complete·approved 2017
Wastewater Treatment System Rehabilitation
$100.0KSemans · Wastewater
complete·approved 2017
Cowichan Water Supply Structured Decision Model (SDM) Development
$100.0KDuncan · Drinking Water
complete·approved 2017
Installation of Accessibility Improvements at Bus Service Stops
$100.0KOakville · Public Transit
complete·approved 2017
LaSalle Corridor Study
$100.0KGreater Sudbury · Active Transportation
complete·approved 2017
Pedestrian Wayfinding Signage
$100.0KThunder Bay · Public Transit
complete·approved 2017
Installation of eleven LED outdoor message signs at bus stops and two flat panel indoor displays
$100.0KWindsor · Public Transit
complete·approved 2017
Renovations and enhancements at the west end transit terminal
$100.0KWindsor · Public Transit
complete·approved 2017
Renovations and enhancements to the transportation services area, including central dispatch, at the main transit terminal
$100.0KWindsor · Public Transit
complete·approved 2017
Replace a bus wash system with a new system
$100.0KSt. Catharines · Public Transit
complete·approved 2016
Sanitary Sewer - LeBreton Street
$100.0KNeguac · Wastewater
complete·approved 2016
Spirit River Village of Rycroft Flood Control
$100.0KSpirit River No. 133≈ · Disaster Mitigation
complete·approved 2015
Highway 4 Barrier Installation
$100.0KPort Alberni · Highways and Roads
complete·approved 2011
Highway 1 Roadside Barrier Upgrade
$100.0KCobble Hill · Highways and Roads
complete·approved 2011
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Municipality of Chatham-Kent - Planning - Feasibility Study and Fleet Transition Plan Municipality of Chatham-Kent | Chatham-Kent | Capacity Building | complete | $100.4K | $125.5K | 2022 |
| Grid Road Reconstruction Rural Municipality of Grass Lake | Reward | Highways and Roads | complete | $100.3K | $401.4K | 2006 |
| Rivervale and Oasis Sewer Service Pump Replacements Regional District of Kootenay Boundary | Kootenay Boundary | Wastewater | complete | $100.3K | $200.6K | 2017 |
| Pump house and Water Intake Upgrades Jackson's-Cove-Langdon's-Cove-Silverdale | Baie Verte | Drinking Water | complete | $100.2K | $250.5K | 2020 |
| Auxilary Power for the Town's Wastewater Treatment Town of Stewiacke | Stewiacke | Wastewater | complete | $100.1K | $257.4K | 2016 |
| Design and Construction of Graham Creek Stormwater Measures City of Ottawa | Ottawa | Wastewater | complete | $100.1K | $225.0K | 2017 |
| Accessible Woodland Trail Construction County of Northumberland | Northumberland | Active Transportation | complete | $100.1K | $125.1K | 2021 |
| Service improvement plan Réseau de transport de Longueuil (RTL) | Longueuil | Public Transit | complete | $100.1K | $200.1K | 2017 |
| New Sewage Lift Station No.3 Town of Carrot River | Carrot River | Wastewater | complete | $100.0K | $300.1K | 2009 |
| Relocation of the Downtown Terminal City of Sault Ste. Marie | Sault Ste. Marie | Public Transit | complete | $100.0K | $238.8K | 2020 |
| Kings Transit Authority - Phase 1 - Planning Study for Electrification of Transit Tidal Transit Authority | Kings | Capacity Building | underway | $100.0K | $250.0K | 2022 |
| Caboto Centre Upgrades Italian Canadian League of Manitoba Inc. | Winnipeg | Recreation | complete | $100.0K | $250.0K | 2022 |
| The Villa LTC Home Chiller Upgrade The County of Lambton | Lambton | Ventilation | complete | $100.0K | $125.0K | 2021 |
| Creation of 2 pressurized neonatal rooms in the Maisonneuve pavilion (7th floor, D wing) Centre intégré universitaire de santé et de services sociaux de l'Est-de-l'Île-de-Montréal | Montréal | Ventilation | complete | $100.0K | $125.0K | 2021 |
| Caraquet - Regional Generations Centre (Phase 1) Town of Caraquet | Caraquet | Capacity Building | complete | $100.0K | $1.0M | 2020 |
| Central Kootenay - Galena Trail Restoration Regional District of Central Kootenay | Central Kootenay Regional District - Electoral H≈ | Active Transportation | complete | $100.0K | $200.0K | 2020 |
| Replacement of Bus Shelters City of Sault Ste. Marie | Sault Ste. Marie | Public Transit | complete | $100.0K | $250.0K | 2020 |
| Municipality of the County of Richmond - Arichat Water Treatment Plant Upgrades Municipality of the County of Richmond | Richmond | Drinking Water | complete | $100.0K | $250.0K | 2019 |
| LED Lighting Upgrades at Approximately 42 Wastewater Pumping Stations Across the City City of Ottawa | Ottawa | Wastewater | complete | $100.0K | $200.0K | 2018 |
| West Side Pond Rehabilitation and Sediment Cleanout Corporation of the Municipality of Clarington | Clarington | Wastewater | complete | $100.0K | $200.0K | 2018 |
| Separation of sewers on Lorne/Gladstone/Melrose/Henry/William Avenues Municipality of Leamington | Leamington | Wastewater | complete | $100.0K | $200.0K | 2018 |
| Quantification of ridership through the use of automatic passenger counters City of Windsor | Windsor | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Installation of 60 Pedestrian Countdown Signal Heads Corporation of the City of London | London | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Saskatchewan Highway Water and Sewer Renewal Municipality of Westlake-Gladstone | WestLake-Gladstone≈ | Drinking Water | complete | $100.0K | $300.0K | 2017 |
| Oil City/Oil Springs Reservoir Upgrades Township of Enniskillen | Oil Springs | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Replace 15 Main Valves Within the Water Distribution System Township of Hornepayne | Hornepayne | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Assessment, Construction and Implementation of a Drinking Water System Dead-End Looping Strategy in the Central Pressure Zone Town of Newmarket | Newmarket | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Replace existing water treatment control system at all three facilities to extend asset life through online asset management Corporation of the Town of Mono | Mono | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Thornbury Wastewater Treatment Plant Roof and Heating, Ventilation and Air Conditioning (HVAC) Replacement Town of The Blue Mountains | The Blue Mountains | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Replacement of Maple Street Storm Sewer - Replacing 110m of storm sewer between Maple St. & McKay Crt. Town of Collingwood | Collingwood | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Village of Sombra Main Pumping Station Rehabilitation Township of St. Clair | St. Clair | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Village of Port Lambton Main Pumping Station Rehabilitation Township of St. Clair | St. Clair | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Sanitary Sewer Trenchless Repairs (Township Wide Backlog) Township of St. Clair | St. Clair | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Brighton Street new storm sewer from Garnet Street to Facer Street Corporation of the City of St. Catharines | St. Catharines | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Structural relining of 300mm watermain at the Flora Street river crossing. The Corporation of the Town of Carleton Place. | Carleton Place | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Water Treatment Plant and Reservoir Upgrade Town of Mossbank | Mossbank | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Water Supply System Pipeline Upgrade Village of Englefeld | Englefeld | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Wastewater Treatment System Rehabilitation Village of Semans | Semans | Wastewater | complete | $100.0K | $200.0K | 2017 |
| Cowichan Water Supply Structured Decision Model (SDM) Development Regional District of Cowichan Valley | Duncan | Drinking Water | complete | $100.0K | $200.0K | 2017 |
| Installation of Accessibility Improvements at Bus Service Stops Town of Oakville | Oakville | Public Transit | complete | $100.0K | $200.0K | 2017 |
| LaSalle Corridor Study City of Greater Sudbury | Greater Sudbury | Active Transportation | complete | $100.0K | $200.0K | 2017 |
| Pedestrian Wayfinding Signage Corporation of the City of Thunder Bay | Thunder Bay | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Installation of eleven LED outdoor message signs at bus stops and two flat panel indoor displays City of Windsor | Windsor | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Renovations and enhancements at the west end transit terminal City of Windsor | Windsor | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Renovations and enhancements to the transportation services area, including central dispatch, at the main transit terminal City of Windsor | Windsor | Public Transit | complete | $100.0K | $200.0K | 2017 |
| Replace a bus wash system with a new system Corporation of the City of St. Catharines | St. Catharines | Public Transit | complete | $100.0K | $200.0K | 2016 |
| Sanitary Sewer - LeBreton Street Village of Neguac | Neguac | Wastewater | complete | $100.0K | $200.0K | 2016 |
| Spirit River Village of Rycroft Flood Control Municipal District of Spirit River | Spirit River No. 133≈ | Disaster Mitigation | complete | $100.0K | $300.0K | 2015 |
| Highway 4 Barrier Installation Government of British Columbia | Port Alberni | Highways and Roads | complete | $100.0K | $200.0K | 2011 |
| Highway 1 Roadside Barrier Upgrade Government of British Columbia | Cobble Hill | Highways and Roads | complete | $100.0K | $200.0K | 2011 |