44projects·$45.2Mfederal of $57.2M eligible
Upgrade of the boiler room and replacement of the storm and sanitary drainage network
$6.6MMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of interior finishes
$3.7MMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the exterior envelope
$2.7MMontréal · Education, Training and Childcare
complete·approved 2023
Renovation of the outer envelope
$2.6MMontréal · Education, Training and Childcare
complete·approved 2023
Heating, ventilation and air conditioning system replacement
$2.2MMontréal · Ventilation
complete·approved 2021
Renovation of Sanitary Blocks and Change Rooms - Phase 1
$1.8MMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the outer casing
$1.4MMontréal · Education, Training and Childcare
complete·approved 2021
Boiler room upgrade and replacement of the storm and sanitary drainage network
$1.3MMontréal · Education, Training and Childcare
complete·approved 2021
School yard renovation and soil rehabilitation project - Phase 2
$1.3MMontréal · Education, Training and Childcare
complete·approved 2021
Gymnasium Renovation
$1.2MMontréal · Education, Training and Childcare
complete·approved 2021
Renovation project of the schoolyard pavement and exterior staircases and the storm drainage network
$1.2MMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading the boiler room
$1.1MMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the outer casing
$1.1MMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the boiler room
$1.0MMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading the Boiler Room and Electrical Service
$1.0MMontréal · Education, Training and Childcare
complete·approved 2021
Schoolyard Pavement Renovation (Phase 2)
$963.3KMontréal · Education, Training and Childcare
complete·approved 2023
Upgrade of the boiler room and replacement of the storm and sanitary drainage network
$894.4KMontréal · Education, Training and Childcare
complete·approved 2021
Roof replacement
$860.0KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of the drinking water distribution network - Phase 2
$825.6KMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the schoolyard pavement
$825.6KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of the drinking water system and upgrading of a crawl space
$818.7KMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of sanitary blocks and changing rooms
$798.1KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of windows and spandrels
$756.8KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of security and intrusion system and emergency lighting
$653.6KMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of sanitary blocks (Phase 1)
$653.6KMontréal · Education, Training and Childcare
complete·approved 2021
Security, intrusion and ceiling replacement
$650.9KMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of sanitary blocks
$643.3KMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of sanitary blocks
$619.2KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of electrical input and emergency lighting
$550.4KMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the palestra
$526.2KMontréal · Education, Training and Childcare
complete·approved 2023
Renovation of sanitary blocks
$437.5KMontréal · Education, Training and Childcare
complete·approved 2021
Roof replacement
$412.8KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of fire detection and alarm systems and addition of intercommunication systems
$347.5KMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading of supply and distribution water (domestic water)
$344.0KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of fire alarm and intercommunication systems
$344.0KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of the drinking water network and upgrading of the anti-backflow device
$337.1KMontréal · Education, Training and Childcare
complete·approved 2021
Replacement of the drinking water distribution network and sanitary and storm drainage
$331.0KMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading of the backflow preventer, the meter, the water cut-off system and the domestic water inlet valve and the drinking water distribution network
$264.9KMontréal · Education, Training and Childcare
complete·approved 2021
Roof replacement
$233.1KMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading of backflow prevention devices, meter, water cut-off system and domestic water inlet valve
$206.4KMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading of the Backflow Prevention Device (BPD), the Meter, the Water Shut-Off System and the Domestic Water Inlet Valve
$206.4KMontréal · Education, Training and Childcare
complete·approved 2021
Bringing anti-backflow devices up to standard
$185.6KMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading of backflow prevention devices, meter, water cut-off system and domestic water inlet valve
$115.5KMontréal · Education, Training and Childcare
complete·approved 2021
Upgrading of the anti-backflow device
$109.2KMontréal · Education, Training and Childcare
complete·approved 2021
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Upgrade of the boiler room and replacement of the storm and sanitary drainage network Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $6.6M | $8.3M | 2021 |
| Replacement of interior finishes Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $3.7M | $4.6M | 2021 |
| Renovation of the exterior envelope Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $2.7M | $3.4M | 2023 |
| Renovation of the outer envelope Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $2.6M | $3.2M | 2023 |
| Heating, ventilation and air conditioning system replacement Centre de services scolaire de Montréal (CSSDM) | Montréal | Ventilation | complete | $2.2M | $2.8M | 2021 |
| Renovation of Sanitary Blocks and Change Rooms - Phase 1 Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.8M | $2.3M | 2021 |
| Renovation of the outer casing Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.4M | $1.9M | 2021 |
| Boiler room upgrade and replacement of the storm and sanitary drainage network Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.3M | $1.7M | 2021 |
| School yard renovation and soil rehabilitation project - Phase 2 Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.3M | $2.0M | 2021 |
| Gymnasium Renovation Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.2M | $1.5M | 2021 |
| Renovation project of the schoolyard pavement and exterior staircases and the storm drainage network Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.2M | $1.7M | 2021 |
| Upgrading the boiler room Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.1M | $1.4M | 2021 |
| Renovation of the outer casing Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.1M | $1.3M | 2021 |
| Renovation of the boiler room Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.0M | $1.3M | 2021 |
| Upgrading the Boiler Room and Electrical Service Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $1.0M | $1.3M | 2021 |
| Schoolyard Pavement Renovation (Phase 2) Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $963.3K | $1.2M | 2023 |
| Upgrade of the boiler room and replacement of the storm and sanitary drainage network Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $894.4K | $1.1M | 2021 |
| Roof replacement Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $860.0K | $1.1M | 2021 |
| Replacement of the drinking water distribution network - Phase 2 Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $825.6K | $1.0M | 2021 |
| Renovation of the schoolyard pavement Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $825.6K | $1.0M | 2021 |
| Replacement of the drinking water system and upgrading of a crawl space Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $818.7K | $1.0M | 2021 |
| Renovation of sanitary blocks and changing rooms Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $798.1K | $997.6K | 2021 |
| Replacement of windows and spandrels Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $756.8K | $946.0K | 2021 |
| Replacement of security and intrusion system and emergency lighting Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $653.6K | $817.0K | 2021 |
| Renovation of sanitary blocks (Phase 1) Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $653.6K | $817.0K | 2021 |
| Security, intrusion and ceiling replacement Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $650.9K | $813.7K | 2021 |
| Renovation of sanitary blocks Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $643.3K | $804.1K | 2021 |
| Renovation of sanitary blocks Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $619.2K | $774.0K | 2021 |
| Replacement of electrical input and emergency lighting Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $550.4K | $688.0K | 2021 |
| Renovation of the palestra Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $526.2K | $657.8K | 2023 |
| Renovation of sanitary blocks Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $437.5K | $546.9K | 2021 |
| Roof replacement Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $412.8K | $516.0K | 2021 |
| Replacement of fire detection and alarm systems and addition of intercommunication systems Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $347.5K | $434.4K | 2021 |
| Upgrading of supply and distribution water (domestic water) Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $344.0K | $430.0K | 2021 |
| Replacement of fire alarm and intercommunication systems Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $344.0K | $430.0K | 2021 |
| Replacement of the drinking water network and upgrading of the anti-backflow device Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $337.1K | $421.4K | 2021 |
| Replacement of the drinking water distribution network and sanitary and storm drainage Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $331.0K | $413.7K | 2021 |
| Upgrading of the backflow preventer, the meter, the water cut-off system and the domestic water inlet valve and the drinking water distribution network Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $264.9K | $331.1K | 2021 |
| Roof replacement Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $233.1K | $291.3K | 2021 |
| Upgrading of backflow prevention devices, meter, water cut-off system and domestic water inlet valve Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $206.4K | $258.0K | 2021 |
| Upgrading of the Backflow Prevention Device (BPD), the Meter, the Water Shut-Off System and the Domestic Water Inlet Valve Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $206.4K | $258.0K | 2021 |
| Bringing anti-backflow devices up to standard Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $185.6K | $232.0K | 2021 |
| Upgrading of backflow prevention devices, meter, water cut-off system and domestic water inlet valve Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $115.5K | $144.4K | 2021 |
| Upgrading of the anti-backflow device Centre de services scolaire de Montréal (CSSDM) | Montréal | Education, Training and Childcare | complete | $109.2K | $136.5K | 2021 |