249projects·$1.7Bfederal of $4.6B eligible
Northwest Transmission Line
$130.0MVictoria · Green Energy
complete·approved 2009
Pointe du Bois Renewable Energy (PREP)
$114.2MPinawa · Green Energy
underway·approved 2022
Prince George to Terrace Capacitors Project: Enabling Electrification of Industry
$97.0MBurns Lake +3 · Green Energy
underway·approved 2020
Powerplant Upgrades and Replacements in Cambridge Bay, Gjoa Haven, Igloolik and Iqaluit
$94.1MCambridge Bay +3 · Green Energy
underway·approved 2021
Yukon Green Energy Legacy
$71.0MWhitehorse · Green Energy
complete·approved 2009
Portage Area Capacity Enhancement (PACE)
$70.9MPortage la Prairie +1 · Green Energy
underway·approved 2022
Construction of a first cellulosic biofuel production plant in Varennes, Quebec to convert non-recyclable, non-compostable waste materials
$70.0MVarennes · Green Energy
underway·approved 2020
Peace Region Electricity Supply
$57.5MFort St. John · Green Energy
complete·approved 2018
Meadow Lake Tribal Council Bioenergy
$52.5MMeadow Lake · Green Energy
complete·approved 2019
Northumberland Strait Submarine Transmission System
$45.7MBorden-Carleton · Green Energy
complete·approved 2015
Modification of Hydro-Québec's facilities in Inukjuak to integrate and optimize the hydroelectricity generated from the Innavik power station
$34.5MInukjuak · Green Energy
complete·approved 2021
New Puvirnituq Diesel Power Plant
$31.0MPuvirnituq · Green Energy
underway·approved 2021
Inuvik Wind Generation
$30.0MInuvik · Green Energy
complete·approved 2018
Summerside Solar and Storage Integration
$26.3MSummerside · Green Energy
complete·approved 2019
Retrofit of Ralph Pickard Bell Library - Mount Allison University
$26.0MSackville · Green Energy
underway·approved 2022
Expansion Project for the Biomethanization Facility of the SÉMECS (Société d'économie mixte de l'est de la couronne sud)
$25.2MVarennes · Green Energy
complete·approved 2019
New Brunswick Community College -Saint John Campus Redevelopment
$22.9MSaint John · Green Energy
underway·approved 2022
Stewart-Keno Transmission Line Rehabilitation
$21.7MMayo · Green Energy
complete·approved 2019
Cape Breton University - Centre for Discovery and Innovation
$20.0MCape Breton · Green Energy
underway·approved 2023
First Nations Housing Retrofit
$19.7MUndefined≈ · Green Energy
underway·approved 2019
Northumberland Strait Submarine Transmission System (top-up)
$19.0MBorden-Carleton · Green Energy
complete·approved 2016
Sade Initiative
$18.0MWatson Lake · Green Energy
underway·approved 2024
Taltson Hydroelectric Facility Major Overhaul
$17.8MEnterprise +4 · Green Energy
complete·approved 2019
CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2
$16.7MCape Breton · Green Energy
approved·approved 2023
Yukon Grid Scale Battery Energy Storage System
$16.5MWhitehorse · Green Energy
underway·approved 2019
Skinners Pond Transmission Line
$16.3MSherbrooke +1 · Green Energy
approved·approved 2020
Health and Social Innovation Centre - UNB Saint John
$15.2MSaint John · Green Energy
underway·approved 2022
BC Hydro Customer Connection Project - Westcoast Energy Inc. - Compressor Station CS16
$15.0MPeace River · Green Energy
underway·approved 2023
BC Hydro Customer Connection Project - Westcoast Energy Inc. - Compressor Station N5
$15.0MHudson's Hope · Green Energy
underway·approved 2023
The Mauricie Organic Waste Processing Centre
$14.7MSaint-Étienne-des-Grès · Green Energy
underway·approved 2020
Fort Garry District Energy Upgrades
$14.1MWinnipeg · Green Energy
underway·approved 2021
SaskPower - Battery Energy Storage System (BESS)
$13.1MRegina · Green Energy
complete·approved 2021
Haeckel Hill Wind Farm
$13.1MWhitehorse · Green Energy
complete·approved 2021
Birtle Transmission Line
$12.0MEllice-Archie +1 · Green Energy
complete·approved 2019
Ulkatcho First Nation - Anahim Lake Solar PV and Energy Storage
$11.9MAnahim Lake · Green Energy
underway·approved 2023
BC Hydro - Customer Connection Project: Creative Energy Decarbonization
$11.3MVancouver · Green Energy
underway·approved 2022
Housing Nova Scotia Public Housing Building Envelope and Systems Deep Energy Retrofit
$11.0MUndefined≈ · Green Energy
underway·approved 2019
Calgary Downtown District Energy
$10.0MCalgary · Green Energy
complete·approved 2007
Turbine and Generator Upgrades at the Snare Forks Powerhouse
$9.5MBehchokö (Rae-Edzo) +2 · Green Energy
complete·approved 2018
Nova Scotia Municipal Electric Utility Community Solar Gardens
$9.0MAntigonish +2 · Green Energy
complete·approved 2021
BC Hydro Customer Connection Project: ARC Resources Electrification
$8.8MDawson Creek +1 · Green Energy
underway·approved 2022
Lutsel Ke New Diesel Power Plant Facility
$8.8MLutsel Ke≈ · Green Energy
complete·approved 2019
Nuxalk Nation - Nooklikonnic Creek Hydropower Project Development Plan
$8.3MNuxalk First Nation≈ · Green Energy
approved·approved 2020
City of Regina - Geothermal Heating Facility
$8.0MRegina · Green Energy
approved·approved 2023
Slemon Park Microgrid
$7.9MSlemon Park · Green Energy
complete·approved 2020
BC Hydro Customer Connection Project: Crew West Septimus and Groundbirch Electrification
$7.5MFort St. John · Green Energy
underway·approved 2023
New Diesel Power Plant Construction in Sachs Harbour
$7.5MSachs Harbour · Green Energy
complete·approved 2018
Greater Vancouver Sewerage and Drainage District - Northwest Langley Wastewater Treatment Plant Renewable Natural Gas Production
$7.3MGreater Vancouver · Green Energy
approved·approved 2023
BC Hydro Customer Connection Project: Surrey Hospital and BC Cancer Centre Electrification
$6.7MSurrey · Green Energy
approved·approved 2023
2021-2022 Electric School Buses
$6.4MCharlottetown +1 · Green Energy
complete·approved 2021
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Northwest Transmission Line Province of British Columbia | Victoria | Green Energy | complete | $130.0M | $605.8M | 2009 |
| Pointe du Bois Renewable Energy (PREP) Manitoba Hydro | Pinawa | Green Energy | underway | $114.2M | $270.0M | 2022 |
| Prince George to Terrace Capacitors Project: Enabling Electrification of Industry BC Hydro | Burns Lake +3 more | Green Energy | underway | $97.0M | $193.9M | 2020 |
| Powerplant Upgrades and Replacements in Cambridge Bay, Gjoa Haven, Igloolik and Iqaluit Qulliq Energy Corporation (QEC) | Cambridge Bay +3 more | Green Energy | underway | $94.1M | $125.4M | 2021 |
| Yukon Green Energy Legacy Yukon Energy Corporation | Whitehorse | Green Energy | complete | $71.0M | $142.0M | 2009 |
| Portage Area Capacity Enhancement (PACE) Manitoba Hydro | Portage la Prairie +1 more | Green Energy | underway | $70.9M | $141.9M | 2022 |
| Construction of a first cellulosic biofuel production plant in Varennes, Quebec to convert non-recyclable, non-compostable waste materials Varennes Cellulosic Ethanol L.P. | Varennes | Green Energy | underway | $70.0M | $728.2M | 2020 |
| Peace Region Electricity Supply BC Hydro | Fort St. John | Green Energy | complete | $57.5M | $115.1M | 2018 |
| Meadow Lake Tribal Council Bioenergy Meadow Lake Tribal Council | Meadow Lake | Green Energy | complete | $52.5M | $70.0M | 2019 |
| Northumberland Strait Submarine Transmission System Province of Prince Edward Island | Borden-Carleton | Green Energy | complete | $45.7M | $91.8M | 2015 |
| Modification of Hydro-Québec's facilities in Inukjuak to integrate and optimize the hydroelectricity generated from the Innavik power station Hydro-Québec | Inukjuak | Green Energy | complete | $34.5M | $88.1M | 2021 |
| New Puvirnituq Diesel Power Plant Hydro-Québec | Puvirnituq | Green Energy | underway | $31.0M | $100.7M | 2021 |
| Inuvik Wind Generation NT Energy | Inuvik | Green Energy | complete | $30.0M | $40.0M | 2018 |
| Summerside Solar and Storage Integration City of Summerside | Summerside | Green Energy | complete | $26.3M | $65.7M | 2019 |
| Retrofit of Ralph Pickard Bell Library - Mount Allison University Mount Allison University | Sackville | Green Energy | underway | $26.0M | $65.0M | 2022 |
| Expansion Project for the Biomethanization Facility of the SÉMECS (Société d'économie mixte de l'est de la couronne sud) Société d'économie mixte de lest de la Couronne Sud (SÉMECS) Inc. | Varennes | Green Energy | complete | $25.2M | $96.1M | 2019 |
| New Brunswick Community College -Saint John Campus Redevelopment New Brunswick Community College | Saint John | Green Energy | underway | $22.9M | $45.9M | 2022 |
| Stewart-Keno Transmission Line Rehabilitation Yukon Energy Corporation | Mayo | Green Energy | complete | $21.7M | $28.9M | 2019 |
| Cape Breton University - Centre for Discovery and Innovation Cape Breton University | Cape Breton | Green Energy | underway | $20.0M | $150.0M | 2023 |
| First Nations Housing Retrofit First Nations Bands of Nova Scotia | Undefined≈ | Green Energy | underway | $19.7M | $26.3M | 2019 |
| Northumberland Strait Submarine Transmission System (top-up) Province of Prince Edward Island | Borden-Carleton | Green Energy | complete | $19.0M | $38.0M | 2016 |
| Sade Initiative First Kaska Utilities LP | Watson Lake | Green Energy | underway | $18.0M | $27.9M | 2024 |
| Taltson Hydroelectric Facility Major Overhaul Northwest Territories Power Corporation (NTPC) | Enterprise +4 more | Green Energy | complete | $17.8M | $23.8M | 2019 |
| CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2 Regional Municipality of Cape Breton | Cape Breton | Green Energy | approved | $16.7M | $43.9M | 2023 |
| Yukon Grid Scale Battery Energy Storage System Yukon Energy Corporation | Whitehorse | Green Energy | underway | $16.5M | $22.0M | 2019 |
| Skinners Pond Transmission Line Prince Edward Island Energy Corporation | Sherbrooke +1 more | Green Energy | approved | $16.3M | $32.5M | 2020 |
| Health and Social Innovation Centre - UNB Saint John University of New Brunswick | Saint John | Green Energy | underway | $15.2M | $38.0M | 2022 |
| BC Hydro Customer Connection Project - Westcoast Energy Inc. - Compressor Station CS16 British Columbia Hydro and Power Authority | Peace River | Green Energy | underway | $15.0M | $30.0M | 2023 |
| BC Hydro Customer Connection Project - Westcoast Energy Inc. - Compressor Station N5 British Columbia Hydro and Power Authority | Hudson's Hope | Green Energy | underway | $15.0M | $30.0M | 2023 |
| The Mauricie Organic Waste Processing Centre Enercycle | Saint-Étienne-des-Grès | Green Energy | underway | $14.7M | $75.7M | 2020 |
| Fort Garry District Energy Upgrades University of Manitoba | Winnipeg | Green Energy | underway | $14.1M | $35.2M | 2021 |
| SaskPower - Battery Energy Storage System (BESS) SaskPower | Regina | Green Energy | complete | $13.1M | $26.2M | 2021 |
| Haeckel Hill Wind Farm Eagle Hill Energy Limited Partnership | Whitehorse | Green Energy | complete | $13.1M | $24.7M | 2021 |
| Birtle Transmission Line Manitoba Hydro | Ellice-Archie +1 more | Green Energy | complete | $12.0M | $24.1M | 2019 |
| Ulkatcho First Nation - Anahim Lake Solar PV and Energy Storage Ulkatcho Energy Corporation | Anahim Lake | Green Energy | underway | $11.9M | $15.8M | 2023 |
| BC Hydro - Customer Connection Project: Creative Energy Decarbonization BC Hydro | Vancouver | Green Energy | underway | $11.3M | $22.7M | 2022 |
| Housing Nova Scotia Public Housing Building Envelope and Systems Deep Energy Retrofit Housing Nova Scotia | Undefined≈ | Green Energy | underway | $11.0M | $23.6M | 2019 |
| Calgary Downtown District Energy City of Calgary | Calgary | Green Energy | complete | $10.0M | $40.4M | 2007 |
| Turbine and Generator Upgrades at the Snare Forks Powerhouse NT Hydro | Behchokö (Rae-Edzo) +2 more | Green Energy | complete | $9.5M | $12.7M | 2018 |
| Nova Scotia Municipal Electric Utility Community Solar Gardens Alternative Resource Energy Authority | Antigonish +2 more | Green Energy | complete | $9.0M | $28.0M | 2021 |
| BC Hydro Customer Connection Project: ARC Resources Electrification BC Hydro | Dawson Creek +1 more | Green Energy | underway | $8.8M | $17.6M | 2022 |
| Lutsel Ke New Diesel Power Plant Facility Northwest Territories Power Corporation (NTPC) | Lutsel Ke≈ | Green Energy | complete | $8.8M | $11.7M | 2019 |
| Nuxalk Nation - Nooklikonnic Creek Hydropower Project Development Plan Nuxalk Nation | Nuxalk First Nation≈ | Green Energy | approved | $8.3M | $11.0M | 2020 |
| City of Regina - Geothermal Heating Facility City of Regina | Regina | Green Energy | approved | $8.0M | $20.0M | 2023 |
| Slemon Park Microgrid PEI Energy Corporation | Slemon Park | Green Energy | complete | $7.9M | $24.6M | 2020 |
| BC Hydro Customer Connection Project: Crew West Septimus and Groundbirch Electrification BC Hydro | Fort St. John | Green Energy | underway | $7.5M | $15.0M | 2023 |
| New Diesel Power Plant Construction in Sachs Harbour Northwest Territories Power Corporation (NTPC) | Sachs Harbour | Green Energy | complete | $7.5M | $10.0M | 2018 |
| Greater Vancouver Sewerage and Drainage District - Northwest Langley Wastewater Treatment Plant Renewable Natural Gas Production Greater Vancouver Sewerage and Drainage District | Greater Vancouver | Green Energy | approved | $7.3M | $18.3M | 2023 |
| BC Hydro Customer Connection Project: Surrey Hospital and BC Cancer Centre Electrification British Columbia Hydro and Power Authority | Surrey | Green Energy | approved | $6.7M | $13.3M | 2023 |
| 2021-2022 Electric School Buses Prince Edwarid Island Department of Education and Lifelong Learning | Charlottetown +1 more | Green Energy | complete | $6.4M | $12.8M | 2021 |