1,431projects·$1.4Bfederal of $3.4B eligible
Watermain Replacement
$404.6KPort au Port East · Drinking Water
complete·approved 2016
Station Road Water Extension
$405.1KAvondale · Drinking Water
underway·approved 2023
Accessibility Improvements on Routes 1, 2, 3 & 5
$405.3KSt. John's · Public Transit
complete·approved 2016
Chlorination Upgrades
$407.5KSouthern Harbour · Drinking Water
complete·approved 2021
Water and Sewer, West End - Phase 1, Part B
$407.7KSunnyside (Trinity Bay) · Drinking Water
complete·approved 2009
Town of Burin - Big Pond Chlorination and Water System Improvements
$408.1KBurin · Drinking Water
complete·approved 2019
Phase 4 - Water and Sewer Upgrades
$408.2KIsle aux Morts · Drinking Water
approved·approved 2023
Valley Road Sewer Upgrade
$411.2KCarbonear · Wastewater
complete·approved 2020
Sewage Lift Station Upgrades
$412.1KHappy Valley-Goose Bay · Wastewater
complete·approved 2021
Cabot/Cormack Water Line Upgrade Town of St. Anthony
$412.1KSt. Anthony · Drinking Water
complete·approved 2019
Water and Road Upgrades
$413.9KChannel-Port aux Basques · Drinking Water
complete·approved 2009
Water System Upgrades
$414.0KHappy Valley-Goose Bay · Drinking Water
complete·approved 2016
St. Thomas Line Widening
$414.2KParadise · Highways and Roads
complete·approved 2014
Industrial Water System, Phases 4 & 5
$414.9KComfort Cove-Newstead · Drinking Water
complete·approved 2009
Completion of Transmission Main and Water Tank
$415.1KCampbellton · Drinking Water
complete·approved 2018
McGettigan Boulevard Upgrades
$415.5KMarystown · Drinking Water
complete·approved 2019
Water and Sewer Upgrading
$416.2KArnold's Cove · Drinking Water
complete·approved 2016
Chlorination Building Upgrades
$417.1KSt. Lawrence · Drinking Water
underway·approved 2022
Clearview Heights Upgrading
$417.6KParadise · Highways and Roads
complete·approved 2017
Arena Floor Replacement
$418.1KFortune · Recreation
complete·approved 2016
Mutford's Cove Road - Water and Sewer - Phase 2
$419.8KCrow Head · Highways and Roads
complete·approved 2020
Water and Sewer 2
$420.0KBay Roberts · Drinking Water
complete·approved 2009
Road Reconstruction and Paving - Rectory Avenue/Casey's Lane
$420.3KSpaniard's Bay · Highways and Roads
complete·approved 2023
Water Treatment (Secondary)
$421.5KPasadena · Drinking Water
complete·approved 2016
Water, Sewer and Storm Sewer - Georgetown Road, Gilbert Street, Raymond Heights Storm Sewer, Watermains
$423.1KCorner Brook · Drinking Water
complete·approved 2016
Upgrade waterline - Main Road and Gulch
$424.5KSt. Bride's · Drinking Water
complete·approved 2016
Petten Building Roof Replacement
$425.4KSt. John's · Administration, Emergency and Public Works
complete·approved 2020
Water booster Pumping Station and Water Main Servicing - Skinner
$425.5KPortugal Cove-St. Philip's · Drinking Water
complete·approved 2020
Shoreline Erosion Control - Location 1
$425.6KFortune · Disaster Mitigation
complete·approved 2023
Kitchen's Hill - Water & Sewer System Upgrade
$426.4KHarbour Grace · Drinking Water
complete·approved 2018
Valley Road Water, Sewer and Street Upgrading Final Phase
$426.9KCarbonear · Drinking Water
complete·approved 2021
Water and Sewer Upgrades
$428.7KSpringdale · Drinking Water
complete·approved 2009
Hampton's Hill Water Tower Replacement
$429.7KBishop's Falls · Drinking Water
complete·approved 2016
Expansion & Improvements to Water System
$430.1KWhiteway · Drinking Water
complete·approved 2009
Street Improvements
$431.4KMount Pearl · Highways and Roads
complete·approved 2014
Water Supply Upgrading - Phase 3
$434.2KBaie Verte · Drinking Water
complete·approved 2009
Street Improvements - Cooper Boulevard and Raynham Avenue
$434.4KGander · Highways and Roads
complete·approved 2016
Notley's Drive water and waste water system
$435.2KPort Hope Simpson · Drinking Water
complete·approved 2016
Rural Road Rehabilitation - Central Region
$436.1KLewisporte +1 · Highways and Roads
complete·approved 2019
Proposed Water and Sewer, Phase 4
$439.0KLark Harbour · Drinking Water
complete·approved 2018
Water and Sewer Services Phase 4
$439.4KCarmanville · Drinking Water
approved·approved 2023
Water Main Extension Pound Cove to Templeman Connection
$440.6KNew-Wes-Valley · Drinking Water
complete·approved 2020
Road Restructuring/Resurfacing and Storm Drain Upgrades
$448.9KWabush · Highways and Roads
complete·approved 2018
Watermain Upgrades Phase 4
$450.2KStoneville · Drinking Water
complete·approved 2023
Water and Sewer Phase 2
$450.6KCarmanville · Drinking Water
complete·approved 2016
Russell Heights Reconstruction
$453.0KStephenville · Drinking Water
complete·approved 2023
Street Resurfacing
$453.2KCorner Brook · Highways and Roads
complete·approved 2017
Watermain Extension (Connect Newtown to Valleyfield)
$453.3KNew-Wes-Valley · Drinking Water
complete·approved 2016
High Street Water, Sewer and Storm Upgrade - Phase 1
$453.3KDeer Lake · Drinking Water
complete·approved 2018
Watermain Replacement - Phase 2
$453.4KBurgeo · Drinking Water
complete·approved 2016
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Watermain Replacement Town of Port au Port East | Port au Port East | Drinking Water | complete | $404.6K | $829.9K | 2016 |
| Station Road Water Extension Town of Avondale | Avondale | Drinking Water | underway | $405.1K | $1.0M | 2023 |
| Accessibility Improvements on Routes 1, 2, 3 & 5 City of St. John's | St. John's | Public Transit | complete | $405.3K | $906.8K | 2016 |
| Chlorination Upgrades Town of Southern Harbour | Southern Harbour | Drinking Water | complete | $407.5K | $1.0M | 2021 |
| Water and Sewer, West End - Phase 1, Part B Town of Sunnyside | Sunnyside (Trinity Bay) | Drinking Water | complete | $407.7K | $1.2M | 2009 |
| Town of Burin - Big Pond Chlorination and Water System Improvements Town of Burin | Burin | Drinking Water | complete | $408.1K | $1.0M | 2019 |
| Phase 4 - Water and Sewer Upgrades Town of Isle aux Morts | Isle aux Morts | Drinking Water | approved | $408.2K | $1.0M | 2023 |
| Valley Road Sewer Upgrade Town of Carbonear | Carbonear | Wastewater | complete | $411.2K | $1.0M | 2020 |
| Sewage Lift Station Upgrades Town of Happy Valley-Goose Bay | Happy Valley-Goose Bay | Wastewater | complete | $412.1K | $1.0M | 2021 |
| Cabot/Cormack Water Line Upgrade Town of St. Anthony Town of St. Anthony | St. Anthony | Drinking Water | complete | $412.1K | $1.0M | 2019 |
| Water and Road Upgrades Town of Channel-Port aux Basques | Channel-Port aux Basques | Drinking Water | complete | $413.9K | $1.2M | 2009 |
| Water System Upgrades Town of Happy Valley-Goose Bay | Happy Valley-Goose Bay | Drinking Water | complete | $414.0K | $827.9K | 2016 |
| St. Thomas Line Widening Town of Paradise | Paradise | Highways and Roads | complete | $414.2K | $1.2M | 2014 |
| Industrial Water System, Phases 4 & 5 Town of Comfort Cove-Newstead | Comfort Cove-Newstead | Drinking Water | complete | $414.9K | $1.2M | 2009 |
| Completion of Transmission Main and Water Tank Town of Campbellton | Campbellton | Drinking Water | complete | $415.1K | $1.3M | 2018 |
| McGettigan Boulevard Upgrades Town of Marystown | Marystown | Drinking Water | complete | $415.5K | $1.2M | 2019 |
| Water and Sewer Upgrading Town of Arnold's Cove | Arnold's Cove | Drinking Water | complete | $416.2K | $832.5K | 2016 |
| Chlorination Building Upgrades Town of St. Lawrence | St. Lawrence | Drinking Water | underway | $417.1K | $1.0M | 2022 |
| Clearview Heights Upgrading Town of Paradise | Paradise | Highways and Roads | complete | $417.6K | $1.8M | 2017 |
| Arena Floor Replacement Town of Fortune | Fortune | Recreation | complete | $418.1K | $1.3M | 2016 |
| Mutford's Cove Road - Water and Sewer - Phase 2 Crow Head | Crow Head | Highways and Roads | complete | $419.8K | $1.0M | 2020 |
| Water and Sewer 2 Town of Bay Roberts | Bay Roberts | Drinking Water | complete | $420.0K | $1.3M | 2009 |
| Road Reconstruction and Paving - Rectory Avenue/Casey's Lane Town of Spaniards Bay | Spaniard's Bay | Highways and Roads | complete | $420.3K | $1.3M | 2023 |
| Water Treatment (Secondary) Town of Pasadena | Pasadena | Drinking Water | complete | $421.5K | $952.2K | 2016 |
| Water, Sewer and Storm Sewer - Georgetown Road, Gilbert Street, Raymond Heights Storm Sewer, Watermains City of Corner Brook | Corner Brook | Drinking Water | complete | $423.1K | $2.0M | 2016 |
| Upgrade waterline - Main Road and Gulch Town of St. Bride's | St. Bride's | Drinking Water | complete | $424.5K | $853.7K | 2016 |
| Petten Building Roof Replacement Newfoundland and Labrador Department of Transportation and Infrastructure | St. John's | Administration, Emergency and Public Works | complete | $425.4K | $531.8K | 2020 |
| Water booster Pumping Station and Water Main Servicing - Skinner Town of Portugal Cove-St. Philip's | Portugal Cove-St. Philip's | Drinking Water | complete | $425.5K | $1.1M | 2020 |
| Shoreline Erosion Control - Location 1 Town of Fortune | Fortune | Disaster Mitigation | complete | $425.6K | $1.1M | 2023 |
| Kitchen's Hill - Water & Sewer System Upgrade Town of Harbour Grace | Harbour Grace | Drinking Water | complete | $426.4K | $1.4M | 2018 |
| Valley Road Water, Sewer and Street Upgrading Final Phase Town of Carbonear | Carbonear | Drinking Water | complete | $426.9K | $1.1M | 2021 |
| Water and Sewer Upgrades Town of Springdale | Springdale | Drinking Water | complete | $428.7K | $1.3M | 2009 |
| Hampton's Hill Water Tower Replacement Town of Bishops Falls | Bishop's Falls | Drinking Water | complete | $429.7K | $859.5K | 2016 |
| Expansion & Improvements to Water System Town of Whiteway | Whiteway | Drinking Water | complete | $430.1K | $1.3M | 2009 |
| Street Improvements City of Mount Pearl | Mount Pearl | Highways and Roads | complete | $431.4K | $1.3M | 2014 |
| Water Supply Upgrading - Phase 3 Town of Baie Verte | Baie Verte | Drinking Water | complete | $434.2K | $1.3M | 2009 |
| Street Improvements - Cooper Boulevard and Raynham Avenue Town of Gander | Gander | Highways and Roads | complete | $434.4K | $1.4M | 2016 |
| Notley's Drive water and waste water system Town of Port Hope Simpson | Port Hope Simpson | Drinking Water | complete | $435.2K | $870.4K | 2016 |
| Rural Road Rehabilitation - Central Region Government of Newfoundland and Labrador | Lewisporte +1 more | Highways and Roads | complete | $436.1K | $872.3K | 2019 |
| Proposed Water and Sewer, Phase 4 Town of Lark Harbour | Lark Harbour | Drinking Water | complete | $439.0K | $1.4M | 2018 |
| Water and Sewer Services Phase 4 Town of Carmanville | Carmanville | Drinking Water | approved | $439.4K | $1.1M | 2023 |
| Water Main Extension Pound Cove to Templeman Connection Town of New-Wes-Valley | New-Wes-Valley | Drinking Water | complete | $440.6K | $1.1M | 2020 |
| Road Restructuring/Resurfacing and Storm Drain Upgrades Town of Wabush | Wabush | Highways and Roads | complete | $448.9K | $1.8M | 2018 |
| Watermain Upgrades Phase 4 Local Service District of Stoneville | Stoneville | Drinking Water | complete | $450.2K | $1.1M | 2023 |
| Water and Sewer Phase 2 Town of Carmanville | Carmanville | Drinking Water | complete | $450.6K | $906.8K | 2016 |
| Russell Heights Reconstruction Town of Stephenville | Stephenville | Drinking Water | complete | $453.0K | $1.1M | 2023 |
| Street Resurfacing City of Corner Brook | Corner Brook | Highways and Roads | complete | $453.2K | $1.8M | 2017 |
| Watermain Extension (Connect Newtown to Valleyfield) Town of New-Wes-Valley | New-Wes-Valley | Drinking Water | complete | $453.3K | $906.8K | 2016 |
| High Street Water, Sewer and Storm Upgrade - Phase 1 Town of Deer Lake | Deer Lake | Drinking Water | complete | $453.3K | $1.4M | 2018 |
| Watermain Replacement - Phase 2 Town of Burgeo | Burgeo | Drinking Water | complete | $453.4K | $906.8K | 2016 |